|
Case Law
Judgment
Shia Kian Eng (trading as Forest Contractors) ...plaintiff v Nakano Singapore (Pte) Ltd ...defendants JUDGMENT: Cur Adv Vult Introduction Background facts 1. The series of disputes involved in this action arises out of the construction
of the development known as Woodsvale Executive Condominium at the junction of Woodlands Avenue 7
and Woodlands Drive 72. The development consists of a total of 13 high-rise apartment blocks. The
developer Woodsvale Land Pte Ltd which appointed the defendants herein, Nakano Singapore (Pte) Ltd (‘Nakano’),
as their main contractor under a design and build contract. Nakano in turn appointed a number of
sub-contractors to carry out different aspects of the works. 2. The plaintiff, Mr Shia Kian Eng, who carries on construction work under the
trade name Forest Contractors, was one such sub-contractor. Hereafter, the plaintiff will be
referred to as Mr Shia when personal reference to him is required but otherwise as far as business
and contractual matters are concerned, the plaintiff will be referred to as Forest. 3. Forest was employed by Nakano to undertake various types of work at the
project. These works included block wall construction, internal and external wall plastering works,
skim coating works, tiling works, steel-lintel works, floor screeding works, solid brick wall works,
the supply and installation of wire mesh above door frames and the supply of Smartplas Cement. The
relationship between the parties started in July 1998 and ended, badly, in January 2000 when Nakano
terminated Forest’s plastering works and ordered Forest off the site. 4. There are a number of disputes between the parties. Forest has sued for
non-payment, under-payment and damages while Nakano has counter-sued for damages claiming that it
was repudiation on the part of Forest that caused it to terminate Forest’s works before they were
completed and, as a consequence, incur additional expenses to procure the completion of the works.
In addition, Nakano claims that part of Forest’s works were defective and wants reimbursement of
the rectification expenses. 5. In the statement of claim, Forest asked for $2,794,744.61 in payment for the
work it had done (both pursuant to the original contracts and pursuant to variation orders) up to
the date of termination by Nakano. This amount was reduced to $2,041,632.63 as a result of
discussions both before and during the course of the trial. In addition to this amount, Forest
claims damages for wrongful repudiation and interest on late payment of its invoices. Nakano
contends that Forest’s claims are inflated and incorrect and, in any event, it is entitled to set
off against Forest’s claim, its own counterclaim amounting to $2,770,935.44. 6. Among the issues to be determined in this action are the following: (1) what documents evidenced the contracts between the parties; (2) the amount due to Forest for the unpaid balance of work done up to the date
of termination which depends on the determination of the following sub-issues: (a) whether Forest is entitled to be paid additional amounts for extra thick
plaster application on the external walls; (b) whether Forest is entitled to be paid extra for hacking the concrete
surface to form keys; (c) the amount due to Forest in respect of the finishing of the entrance
canopies; (d) whether any amount is due in respect of grouting around door frames; (e) whether Forest is entitled to recover the costs of rectifying debonded
plaster; (f) whether Forest filled in the gaps between lift door jams and the concrete
lift shaft at block 19; (g) whether Forest had to apply over-thick plaster to the internal block
walls and, if so, whether payment for the same is due; (h) whether plastering of separation walls was included in the original scope
of work or was a variation; (3) the amount of previous payments made by Nakano; (4) whether Nakano terminated Forest’s contract wrongfully; (5) if the answer to (4) is in the affirmative, then the issue of damages for
wrongful termination would have to be considered; (6) if the answer to (4) is in the negative, then the issue of damages
recoverable by Nakano would have to be considered and this would include consideration of whether
it acted reasonably in mitigating its loss by employing a company called Acolite to do part of the
rectification work for the defective plaster works and also the area of wall left unplastered at
the time that Forest stopped work. (7) whether, in any event, Forest was in breach of contract in relation to the
works and what, if any, damages are payable to Nakano in relation to such breaches. List of witnesses and important persons and companies referred to in the case 7. For ease of reference, I set out names and descriptions of persons who may be
referred to in this judgment: (a) ‘Acolite’: Acolite Construction (S) Pte Ltd, a company employed by
Nakano to rectify defects in the plaster by using the pin-injection method; (b) ‘BBR’: BBR Construction Systems Pte Ltd, the sub-contractor who put up
the concrete frame of the blocks using a mechanical form work called the Doka system; (c) the defendants’ witnesses: (i) Satoshi Hattori, a general manager in Nakano’s construction department
who acted as the project general manager for this project; (ii) Ling Hea Inn, Nakano’s project manager in charge of finishing work at
the project; (iii) Steven Lee Tiong Chye, a foreman in Nakano’s employ; (iv) Nick Koan Ping Seng, a Nakano foreman; (v) Jonathan Liow Thian Seck, a Nakano foreman; (vi) Teh Teik Seng, a project engineer and site foreman employed by Nakano; (vii) Phyllis Leong Yien Min, an assistant project manager employed by
Nakano; (viii) Quek Leng Keng, a mechanical and electrical co-ordinator employed by
Nakano; (ix) Yamazaki Tatsuaki, a director of Acolite; (x) Law Kong Hoi, a professional engineer employed by Insight Adjusters and
Surveyors Pte Ltd; (xi) Wong Chung Wan (CW Wong), a civil and structural engineer who is manager
of SETSCO Services Pte Ltd; and (xii) Wong Siew Fai (CF Wong), a professional quantity surveyor working for
Barton Associates Pte Ltd; (d) the plaintiff’s witnesses: (i) Shia Kian Eng; (ii) Koon Tack Meng, a site supervisor employed by Forest; (iii) Kumaravalu A/L N Doraisamy (Kumar), a Forest site supervisor; (iv) Kenneth Hugh Jones, a chartered builder and a director of Robinson Jones
Associates Pte Ltd, a firm of building surveyors; and (v) Michael Choo Swee Leng, a project director employed by Forest; (e) Ian McGunnigle, a chartered building surveyor who was engaged by Nakano to
examine a report presented by SETSCO Services and who filed an affidavit of evidence-in-chief but
who was not called by Nakano; and (f) Yu Bee: Yu Bee Construction, a firm carrying on the business of plasterers
in Singapore. Issues relating to Forest’s claim 1. What form did the various sub-contracts between Nakano and Forest take? 8. Forest and Nakano agree that there was no single sub-contract which covered
the works to be carried out by Forest in relation to the project. They differ, however, as to the
form which the various sub-contracts took. Forest’s position is that these were made partly
orally, partly in writing and partly by conduct. Further, during the course of various sub-contract
works, Forest had, pursuant to either written or oral requests from Nakano, carried out additional
and variation works. With reference to the Purchase Orders which Nakano issued, Mr Shia does not
deny signing these Purchase Orders on behalf of Forest. His stand is that these documents were
issued purely for accounting purposes and for processing payments to Forest. The conditions endorsed
on the Purchase Orders were not intended to be, and were not, incorporated as terms of the
sub-contracts. 9. Nakano’s position is that the sub-contracts are wholly in writing and that
they comprise the Purchase Orders issued by Nakano and the various other documents mentioned in
those Purchase Orders. These additional documents varied depending on the sub-contract concerned.
All the Purchase Orders referred to the relevant quotation submitted by Forest. In addition, almost
all referred to a document entitled ‘Conditions of Sub-Contract’ and many referred to an ‘Undertaking
on Hiring of Foreign Workers’. The Purchase Order which has caused the most dispute relates to the
contract for block wall and external wall plastering and that referred, in addition to the documents
just mentioned, to a document entitled ‘Conditions of Purchase’, to one entitled ‘Bills of
Quantity/Schedule of Rates’ and to ‘Drawings’. 10. The Purchase Orders take a standard form. Each of them has a ten digit
identifying number. The first three digits of the identifying numbers of the Purchase Orders in
question were all ‘800’ and the court was informed that these digits were used to indicate
Purchase Orders issued in the 1998 financial year whereas Purchase Orders issued in the following
financial year bore the identifying digits ‘900’. The first sentence of the first paragraph of
each Order reads: ‘We are pleased to issue purchase order to you for the undermentioned works
subject to the following Term and Conditions:’ That sentence is followed by various items including a description of the scope
of work, the contract price, the maintenance period, the dates of commencement and completion and
the item ‘payment terms’ which in each case was described as being ’30 days’. The second
paragraph of each Purchase Order starts: ‘Subject also to the following documents as annexed herewith which form an
integral part of this contract: (a) Conditions of Sub-Contract ...’ and thereafter there are further sub-paragraphs mentioning other documents
including the relevant quotation submitted by Forest. The last sentence of the Purchase Order is in
bold capital letters and states: ‘PLEASE SIGN AND RETURN DUPLICATE COPY TO THIS OFFICE EARLY SO AS TO AVOID
DELAYED PAYMENT’ 11. It is not in dispute that none of the Purchase Orders were issued before
Forest started work on any of the sub-contracts. Mr Shia testified that the sub-contracts arose out
of negotiations between himself, Mr Hattori and Mr Ling based on the scope of work to be done and
quotations that he had given to Nakano in June and July 1998. Also Forest had been requested to do
mock-ups of the plastering works and, after these mock-ups were found to be acceptable, Forest had
been instructed to start work by Nakano’s representatives. The Purchase Orders were, according to
Mr Shia, nowhere in evidence at the time of these discussions or when he started work. They were
only given to him subsequently when he asked how payment was to be made. He was then told that the
Purchase Orders had to be signed in order for him to receive payment. He therefore signed the
documents purely for Nakano’s administrative purposes. 12. Nakano submitted that the Purchase Orders were sent to Forest on varying
dates and that Mr Shia had ample opportunity to raise any objections he had to their terms. Mr Shia,
however, did not raise any such objection. He signed all the Purchase Orders without seeking to vary
any of the terms and conditions. As he did not indicate that he was unhappy with the terms or could
not agree to any of them, Nakano had no reason to believe that Forest did not consider itself bound
by the terms of the Purchase Orders and the terms and conditions of sub-contract attached to them.
When Mr Shia returned the signed Purchase Orders, it was reasonable for Nakano to assume that he had
accepted their terms. 13. Nakano submitted that by attempting to adduce oral evidence to contradict the
written terms and conditions set out in the Purchase Orders, Forest had fallen foul of the parol
evidence rule. I cannot accept this submission. Whilst once it is clear that a contract has been
made wholly in writing, parol evidence is not admissible to add to, vary, subtract from or
contradict the written terms, that rule does not apply when the issue to be determined is whether
the contract is wholly in writing or not. In such a case, the court is entitled to receive evidence
whether parol or otherwise of all the relevant circumstances in order to determine what sort of
contract came into existence. 14. Forest’s stand is that as an acceptance of an offer can be made by conduct,
in this case the sub-contracts had been constituted by Forest’s commencement of work on Nakano’s
instructions and the only written documents that formed part of the sub-contracts were its amended
quotations. In order to combat this submission, Nakano further submitted that even though the
Purchase Orders were issued and signed after works had commenced, the conditions of sub-contract
attached to them formed part of these sub-contracts and had a retrospective effect so as to make the
conditions apply to things done earlier in anticipation of the conclusion of formal documentation.
It relied on Trollope & Colls Ltd. v Atomic Power Construction Ltd [1962] 3 All ER 1035
which held that there was no principle of English law which provided that a contract could not, in
any circumstances, have retrospective effect. In that case the defendants carried out civil
engineering works for the building owner at the request of the plaintiff at a time when the parties
were still negotiating alterations to the tender. Parties only agreed on the form of general
conditions of contract ten months after the defendants started work. The Court held that the
conditions of contract were binding on the parties on the basis that they had been conducting their
transactions with one another for many months on the assumption that the contract would ultimately
be agreed on lines known to both the parties although the final form of various terms of the
proposed contract were still under discussion. In that case the parties had assumed that when the
contract was made, ie when all the terms had been agreed in their final form, the contract would
apply retrospectively to the preceding transactions. 15. In this case, it is not quite so clear that both parties had been in active
negotiation on the form of terms and conditions and had started work on the assumption that these
would eventually be agreed. The evidence given by Mr Shia was that his negotiations with Nakano
related mainly to the type of work to be done and to the rates chargeable by Forest. Although Mr
Hattori asserted in his affidavit that he had told Mr Shia during one of these meetings that the
final contract would be subject to Nakano’s standard terms and conditions, there was no evidence
that, at any time prior to asking Forest to start work on the external plastering, Nakano had
furnished Forest with copies of its standard purchase orders and conditions of sub-contract. Even Mr
Hattori did not go so far as to assert that any of the wording of the conditions in the standard
terms and conditions was discussed with Forest. Further, whilst Forest started external plastering
work in July, the Purchase Order for that sub-contract was dated 12 August 1998 and signed by Mr
Shia on 10 September 1998. Mr Shia in fact asserted that he did not receive it in August 1998 and
that it had been back-dated. He did not object to this, however, as he was anxious to receive
payment and therefore concentrated on signing and returning the document as quickly as possible. 16. It is difficult to accept Nakano’s contention that Forest’s quotations
were accepted on the understanding that formal contracts would follow. Nakano had confirmed that it
was familiar with the practice in the construction industry of using letters of intent that would
usually contain a provision indicating that a formal contract would follow. It conceded that it had
not issued any letter of intent in connection with this contract. As pointed out earlier, nor did
its representatives give Forest a copy of its conditions of sub-contract for the latter’s
consideration. Whilst Forest probably would have expected a written acceptance of its quotations it
would not have expected to be inundated with contractual documents when it had not been given any
such documents prior to commencing work. This would definitely be the case for those quotations
tendered and accepted before 10 September 1998 when Mr Shia signed the Purchase Order for the block
and external plastering works. Nakano could perhaps have argued in respect of the sub-contracts
concluded after 10 September 1998 (by which I mean those in respect of which quotations were
tendered and work started after that date) that they were made on the basis of all the terms of the
relevant Purchase Orders including the conditions of sub-contract since after that date Forest would
have been aware that Nakano did have standard conditions of sub-contract that it wanted to apply to
all its sub-contracts. Nakano has not, however, made any submission that distinguishes the position
in relation to the later sub-contracts. This may be because it is mainly in relation to the
sub-contract for the external plastering works that Nakano is anxious to persuade the court that the
Purchase Order and its attachments formed the entire contract. The issue is not as important for the
other sub-contracts. In any case since no such submission has been made, I must treat all the
sub-contracts as having been concluded on the same basis. 17. In my judgment, the sub-contracts were, as contended by Forest, partly in
writing and partly oral. The written portions of the sub-contracts comprised the quotations and the
original Purchase Orders which Forest signed after commencing the work. It is significant that, as
Nakano pointed out, Mr Shia did not object to any of the terms relating to the works that appeared
on the face of the Purchase Orders. These were the items that had to be agreed in order for a
contract to exist and it is likely that the reason he did not object to them was that these terms
reflected the prior discussions. 18. The above holding, however, does not mean that Forest had agreed to accept as
part of the contract all the documents that were annexed to the Purchase Orders or that the same
were incorporated in the contract simply by being mentioned in the Purchase Orders. I have already
mentioned the difficulties with incorporating the conditions of sub-contract. As regards other
documents, it should be noted that while the Purchase Orders mentioned these various documents as
being annexed to them, not all the documents were in fact so annexed. For example, in the Purchase
Order relating to the external plastering works, among the documents stated as being annexed were
‘Specification’ and ‘Drawings’. It appears from Mr Ling’s evidence that these documents
were not in fact annexed. In his affidavit after listing the documents that had been forwarded under
cover of the Purchase Order, he stated that the drawings had already been shown to Mr Shia and the
specifications were the ones which had been furnished to Nakano by one Mark Tung. It is difficult to
incorporate as part of a contract documents which are not furnished (and not simply shown) by one
party to the other either prior to or at the time of signing of the contract unless there is clear
indication by that other party that he would accept documents subsequently given as part of the
contract. This did not happen in this case. 19. As regards the plastering contract, Nakano’s position is that the
manufacturer’s brochure for the use of the proprietary cement product called ‘Smartplas’ was
incorporated as part of the sub-contract by the reference in the relevant Purchase Order to ‘Specification’
in para 2(d) thereof. This brochure was sent to Nakano by the aforementioned Mark Tung, the vendor’s
representative. The brochure was not supplied by Forest nor was there any evidence that Forest had
seen the same brochure that had been given to Nakano. 20. Forest did not accept that the product brochure was incorporated as part of
the plastering sub-contract by mention of the word ‘Specification’ in the Purchase Order. Forest
did accept that the brochure contained technical information but this in itself did not, Forest
submitted, mean that the word ‘Specification’ referred to that brochure. In fact there was a
great deal of doubt over the precise meaning of the term as used in the Purchase Order. 21. First, the persons in Nakano’s quantity surveying department who prepared
the Purchase Orders had not seen, and would not know of the existence of, this Smartplas brochure.
They were not even aware that Smartplas was the product being used. Further, Nakano gave no evidence
as to who gave the Purchase Orders to Mr Shia to sign and what he was told about documents at that
time. Mr Shia identified Ms Phyllis Leong as the person who handed the Purchase Orders to him but Ms
Leong herself gave no evidence on the circumstances surrounding the preparation of the Purchase
Orders or their submission to Mr Shia. So there was no evidence that when he received the Purchase
Order Mr Shia was informed that the ‘Specification’ mentioned in that document referred to the
Smartplas brochure or that the brochure was attached to the Purchase Order. Mr Hattori in his oral
evidence also appeared to agree that the brochure had not accompanied the Purchase Order. 22. That there was doubt as to what the word ‘Specification’ meant was also
evident from the oral testimony of Mr Ling. He conceded that that word may have meant either item 18
of the specifications in the main contract dealing with plaster work or secondly, a separate set of
specifications that Nakano might have intended to specially prepare for the work to be carried out
by Forest. 23. In view of the confused position relating to the project brochure, I am not
able to hold that it was incorporated as part of the plastering sub-contract between Forest and
Nakano. This does not mean, however, that the contents of the brochure are entirely irrelevant to
this case. Since the brochure contained information about the use of Smartplas, it might be relevant
in considering whether Forest’s workers applied the product properly. It is not relevant, however,
for the purpose of considering what Forest’s contractual obligations consisted of. 2. What is due to Forest in respect of work completed before termination? 24. There is no dispute that Forest is entitled, in principle, to be paid for the
work that it had done prior to the termination of the contract. What is at issue is exactly how much
is due to Forest. The parties have agreed on some items but there are still substantial disputes in
this regard. 25. Forest’s original claim was for $2,794,744.61. Due to agreements before and
during the trial, by the time of submissions, Forest’s claim was reduced to $2,041,632.63
(excluding GST). This sum comprised the unpaid balance for all the original works and variation
works carried out by Forest up to the date of termination. Forest derived this amount in the
following manner: (S$) (S$) (a) Agreed value of original sub-contract
works 5,100,896.76 (b) Agreed/Undisputed variation 34,501.40 (c) Disputed variation 1,309,020.55 6,444,418.71 (d) Less: Previous payment 4,402,786.08 2,041,632.63 ======= 26. It would be noted at once that the parties had agreed on the value of the
original sub-contract works performed by Forest. The dispute over Forest’s payment entitlement is
largely centred on the variation works that Forest claims to have effected. Its original claim for
variation works was for $1,777,669.04. Due to agreements arrived at, the total sum now claimed for
variation works is $1,343,521.95. As shown in the table above, of this sum $1,309,020.55 is disputed
by Nakano. There are eight items which make up this claim. I will deal with them separately. 2.1 Extra over-thickness for external plastering 27. In the original quotation for external plastering, Forest quoted a rate of
$14 per square metre for plastering the internal walls and a rate of $15.50 per square metre for
plastering the external walls. After discussion with Nakano, these rates were revised and the
subsequent quotation issued read, in relation to these items: ‘Plaster – Internal Wall (8mm. plaster with skim coat) S$10.50/m² - External Wall (10mm. plaster without skim coat) S$12.50/m²’ In each case, the words in parenthesis describing the thickness of plaster
required had not appeared in the original quotation. 28. Forest’s case is that in respect of the external walls, it was
contractually obliged to apply plaster only to a thickness of 10 mm. Its price of $12.50 per square
metre was based on this thickness of plaster being all that was needed for the external walls. The
claim for over-thickness is founded on the assertion that in order to provide a smooth and vertical
surface over an uneven concrete substrate, Forest found that it had to apply plaster that had a
thickness greater than 10 mm. As a result, it incurred extra costs that it contends it should be
compensated for. 29. Forest pointed out that originally Nakano had intended only to apply a skim
coat over the concrete substrate, not to apply plaster. As it turned out, however, Nakano was not
able to achieve the smooth surfaces it had expected and therefore, as Mr Hattori agreed, it
eventually decided to use plaster to cover the uneven surfaces. Forest was not, however, informed
that this was the purpose of the plastering sub-contract. 30. Prior to the application of the plaster, Forest was required to put in place
corner beads and level pegs. A mock-up was conducted to observe and approve its sequence of work and
representatives of Nakano and the developer were present to inspect the work carried out at the
mock-up. The application of the plaster according to the alignment marked out and delineated by the
corner beads and level pegs was intended to ensure that the plastering work was sufficiently flat
and smooth. In short, Forest submitted, the walls were not meant to remain uneven after plastering.
In the course of applying the plaster, however, it became clear that it was not possible to achieve
the flat and smooth plastered surface by applying only 10 mm of plaster owing to the non-verticality
of the concrete walls and the introduction of groove lines. 31. Forest pointed out that verticality reports prepared by Nakano itself
indicated that the concrete walls were not vertical and had indentations and protrusions. During
cross-examination, Mr Hattori conceded to deviations of up to 20 mm. Further, in some locations, the
reports seem to show that there were deviations of up to 32 mm. 32. In August 1998, Mr Shia approached Mr Ling at the site office and informed
him that the concrete walls were not vertical. At that time most of the blocks were roughly about
four storeys high. Nakano did not take Mr Shia’s comments very seriously. It considered that they
were a method of trying to obtain an increased rate for the external plastering. Mr Shia repeated
his observation of the non-verticality of the walls in a letter of 16 November 1998. This stated
that as a result Forest had had to lay plaster of a minimum thickness of 15 mm and, in many cases,
had laid plaster of 45 mm thickness. It put the average thickness of the plaster laid to that date
as 25 mm and quoted a rate of $22.50 per square metre for the total thickness of plaster laid (ie
the original rate of $12.50 per square metre for the contracted thickness of 10 mm plus an
additional $10 per square metre for the over-thickness). Forest asked Nakano to issue it with a
formal variation and confirmation of the new rate. As this letter was not responded to, a reminder
was sent a month later. That was ignored too. 33. Forest submitted that Nakano should and could have made further
investigations based on what Forest had told it. It further submitted that this was not done because
Nakano had decided that the application of over-thick plaster was a solution to deviations in
verticality. Counsel pointed to a letter that Nakano had written to BBR in September 1999
complaining about a slanting wall which BBR had not rectified and stating that Nakano would carry
out rectification works by getting its plastering contractor to thicken the wall. When shown this
letter, Mr Hattori agreed that he had decided by September 1999 that the solution to deviations in
verticality was to apply extra-thick plaster. He also conceded that it was more expensive to rectify
concrete structures directly than to cover the unevenness with plaster. Mr Hattori maintained,
however, that the concrete structure needed to be rectified only when the deviation was out of the
tolerance and that in this case there had been no verticality problems. 34. Nakano takes the position that Forest’s claim for the application of
over-thick plaster is a fictitious one. It pointed out that Forest had not produced any records of
the thickness of plaster that was applied to the external walls. Nakano therefore submitted that
there was no evidence that Forest had in fact plastered an average thickness of 25 mm throughout the
entire expanse of all the external walls or that such thickness was necessitated by the alleged
non-verticality of the walls. Nakano relied on the report that Mr CW Wong of SETSCO had prepared.
This gave an analysis of samples of plaster which had been extracted from the reinforced concrete
walls at different locations at the first storey level. According to the report, these samples
showed that the overall thickness of the plaster fluctuated widely from 8 mm to 28 mm. The number of
layers also varied: there were between one and three layers. Nakano used this observation to submit
that Forest’s claim that it had plastered three coats throughout the external walls was untrue. It
should be noted, however, that SETSCO took only seven samples from the external walls. In view of
the wide expanse covered by the external walls (the parties agreed that Forest’s work covered
59,257.50 square metres of external wall), seven samples do not seem to me to be a sufficient number
for one to infer that the samples are, in relation to thickness, representative of the total work
carried out. Further, these samples were taken from the lowest level where the deviations in
verticality, if any, would have been the least. No samples were taken from the higher levels where
deviations in verticality would have increased. 35. Nakano also relied on readings of plaster thickness taken by Insight
Surveyors for each level of several blocks chosen at random. From these readings, it appeared that
Forest did not start with a minimum of 10 mm of plaster but started with 14 mm at the highest point.
Nakano submitted that this made it clear that the over-thickness applied by Forest was more the
result of poor supervision and workmanship than done to address any alleged verticality problem.
Nakano’s position was that 10 mm was an average requirement rather than a fixed requirement and
that if Forest had started at 5 mm at the highest point it would only have had to plaster an average
of 10.7 mm as demonstrated by the readings of one of the elevations of block 17. In the alternative,
Nakano submitted that if the court held that 10 mm was a fixed requirement, then the average
thickness of the plaster would have been 15.7 mm. 36. The results of the survey made by Insight Surveyors were exhibited in
evidence. The survey covered one entire elevation of each of the 14 storeys of three of the blocks
of the project and two entire elevations of a fourth block. This was a better sampling than that
carried out by SETSCO. It showed that the thickness of plaster applied at block 17 varied between 14
mm and 20 mm. The average thickness of the plaster was 19.7 mm. For block 15, the thickness of
plaster varied between 11 mm and 20 mm giving an average thickness of 14.4 mm. For block 9C, the
thickness of the plaster varied between 14 mm and 24 mm giving an average thickness of 18.2 mm. For
block 9C, the thickness of plaster laid varied between 15 mm and 24 mm giving an average of 19.5 mm
in thickness. 37. I accept the submission made by Forest that they were required by the
sub-contract to plaster a fixed quantity of 10 mm of plaster over the external walls. This appears
to me to be the plain reading of the sub-contract. The depth of the plaster required was
specifically added to the original quotation. It was also specified that this depth had to be
achieved ‘without skim coat’ thus indicating that it was a specific depth that was wanted. If it
had been intended, as Nakano submitted, that this depth was to be an average depth, the word ‘average’
would have been inserted in the quotation. I also accept the evidence of Forest that due to
unevenness and variations in verticality the actual thickness of plaster applied exceeded the fixed
quantity. This evidence was supported by the verticality surveys carried out by Nakano itself and
also by the survey of Insight Surveyors. Mr Hattori made much of the fact that Forest did not start
with the alleged minimum plaster thickness of 10 mm at the highest point and also put forward an
alternative method of plastering. His method was effectively discredited during cross-examination. 38. I accept that due to variations in the verticality of the external walls and
their unevenness Forest had to apply more than 10 mm of plaster to the walls in order to achieve an
even and vertical effect. The difficulty that arises is in determining exactly how much extra
plaster was applied. Forest’s claim is based on an average thickness of 25 mm of plaster being
applied but this figure is not derived from records kept during the plastering work. There is no
full survey of the thickness of plaster applied to all the elevations of all 13 blocks. Insight
Surveyors’ report, dealing with four full elevations taken from three blocks, showed an average
thickness per elevation of 19.7 mm, 14.4 mm, 18.2 mm and 19.5 mm respectively. 39. Forest derived its figures for the amount of plaster applied by calculations
based on the amount of Smartplas cement premix that it had purchased and had delivered to the site
for the purpose of the plastering works. Mr SF Wong, a professional quantity surveyor himself,
agreed that a quantity surveyor can calculate a total quantity of premix required for a particular
job if he knows what the material volume yield is. In this case, the volume yield of Smartplas, as
obtained from the manufacturer’s brochure, was 0.6m³ per metric ton. Using this figure, Mr Jones,
Forest’s expert, computed the total volume of internal wall plastering that was applied by
multiplying the total quantity in metric tons by the yield per metric ton. In respect of the
external walls, similar calculations were carried out by Forest’s quantity surveyor, Mr Manolo
(who did not give evidence), and verified by Mr Choo. The calculations as such were not discredited
by cross-examination. The issue that remains is whether I should rely on such calculations rather
than on physical measurements. I see no good reason not to accept the calculations since the
quantity of plaster purchased was not challenged and the method of making the calculations was a
valid one. There was a point raised in court regarding possible wastage of the plaster during use
but I accept Forest’s submission that this wastage would have been diminis. Certainly no evidence
was adduced by Nakano to establish widespread wastage of plaster exceeding the 10% allowance for
wastage already included in the calculations. 40. Accepting that 25 mm of plaster, instead of the contracted 10 mm, was applied
to the external walls, the next issue is at what rate Forest should be paid for the additional 15 mm
of plaster. It has claimed $10 per square metre on the basis that its total cost for all 25 mm
(including a profit element of 10%) was $22.50 and thus the cost of the extra 15 mm after deducting
the original price of $12.50 per square metre was $10 per square metre. 41. Mr SF Wong suggested an alternative rate of $8.75 per square metre for the
extra 15 mm of plaster applied. This was based on a calculation that to apply 25 mm of plaster would
cost $21.25 per square metre if three layers of plaster were applied. If two layers of plaster were
applied then the cost would be $16.25 per square metre. In either case, Mr Wong’s calculation did
not include any figure for profit on the work. As Forest submitted, it would be entitled to a profit
element as part of its rate. It should also be noted that during cross-examination Mr Wong accepted
that two coats of plaster on top of the base coat would have to be applied in order to bring the
thickness up to 25 mm. Thus, the material rate suggested by him would be $21.25 per square metre and
not $16.25 per square metre. If a profit element of 10% is added to $21.25, the total rate would be
$23.375 which would be more than Forest’s claimed rate of $22.50 per square metre. Accordingly I
accept Forest’s rate of $10 per square metre for the extra 15 mm of plaster. 42. The next question is to what area this rate should be applied. In the course
of proceedings, the parties agreed that the area of external walls worked on by Forest was
59,257.50. They also agreed that Forest had worked on 5,551 square metres of walls in the lift
lobbies. The issue here is whether the lift lobby walls should be considered as part of the external
walls for the purpose of this rate or whether they should be considered as part of the internal
walls to which a lower rate was applicable. The submission made by Nakano was that Forest had
carried out plastering and skim coating on the lift lobby walls and this activity was consistent
with classifying those walls as internal walls as, under the internal plastering sub-contract, skim
coating was required for internal walls. Further, since these walls were not exposed to the weather,
they should be classified as internal walls rather than external walls. 43. Forest did not answer the above submissions. It appears to me that Nakano’s
argument is correct and since the lift lobby walls have little exposure to the weather, they should
be treated as internal walls. Further, there was no evidence on non-verticality of lift walls which
would have required correction by an application of thicker plaster. There is no need, therefore, to
include the area of the lift lobby walls as part of the area for which Forest should be paid for the
application of extra thick plaster. 44. Accordingly, the amount to be paid to Forest for the extra thickness of
plaster applied to the external walls should be $10 x 59,257.50 ie $592,575. I award this sum to
Forest. It is payable in full and without any deduction for retention. 2.2 Hacking to form keys 45. Forest claimed $17,118.86 for hacking the concrete surface of the external
walls to form keys to assist in adhesion of the plaster to the substrate. Nakano disputed this claim
on the basis that it was part of Forest’s duty to do all that was necessary to ensure good
plastering workmanship and that since the sub-contract for the plastering works was a ‘supply and
install’ contract, and as Forest claimed to be specialist plasterers, Nakano left it entirely to
Forest to carry out whatever preparation the latter deemed appropriate to ensure good workmanship.
Any hacking which Forest did, therefore, formed part of its plastering costs and could not be
charged for separately. 46. Forest argued that preparation of surfaces and actual plaster works were two
distinct items of work. This was reflected in the main contract between Nakano and the developer in
that the preparation of surfaces appeared under item 11 whilst the plaster works appeared separately
as item 18. Further, item 11 specifically made it Nakano’s obligation to hack off projecting fins
on the concrete work, to clean the concrete surface of dirt and incompatible materials and to
thoroughly hack surfaces to form a key. The first two of the foregoing were not sub-contracted to
Forest but carried out by Nakano itself or through BBR. As Mr Hattori acknowledged in court, item 18
dealing with plaster works said nothing about the formation of keys or the provision of a bonding
agent. 47. Mr Hattori tried to avoid the implications of the separate categorisation by
stating that the main contract specifications with regards to plastering work were only relevant if
conventional cement/sand plaster was used. Whilst it is true that the main contract envisaged
conventional cement/sand plaster being applied, this does not mean that simply because a different
plastering material is used hacking need not be separately specified if it is to be carried out by
the plasterer since, in any case, hacking does not appear as part of the item relating to
plastering. Secondly, Forest’s contract was to ‘supply and install’ not to ‘design and build’
unlike the contract Nakano had. Although Forest suggested the premix material, the decision whether
it should be used or not lay with Nakano and Nakano had therefore the obligation to determine what
sort of surface was required for such material and who should provide the necessary surface. 48. Forest submitted that hacking to form keys or the application of a bonding
agent were components of work that must, as matter of practice, be clearly specified. It
relied on Rule 15.04(b) of Standard Method of Measurement of Building Works (SMM Rules) which states
that any special treatment of a base (for example hacking, applying bonding agent) and the nature of
the surface finish should be given in each description or in the relevant sub-heading for the work. 49. In this case, none of the sub-contract documents made express mention of any
requirement to form keys or provide a onding agent. Nakano’s position was that since Forest had
proposed the use of Smartplas, it had a duty to consider the specifications of that material and to
carry out such surface preparation as was stipulated to be necessary by those specifications. In
relation to this argument, as I have stated above, the ultimate decision as to whether Smartplas
should be used lay with Nakano. Nakano had overall design responsibility and therefore had to
consider how Smartplas would work in conjunction with the structural conditions found on site. It
would therefore be up to Nakano to determine whether hacking was required for Smartplas and, if so,
to so specify in its contract with Forest. It would be noted also that according to the product
information on the Smartplas brochure, that material only required a bonding agent or hacking to
form keys if the thickness of plaster to be applied exceeded 12 mm. In this case, the specified
thickness was 10 mm and therefore even if it was Forest’s obligation to consider hacking, Forest
would not originally have concluded that hacking was required. 50. In my opinion, hacking was not included as part of the sub-contract. When
Nakano requested Forest to hack the concrete surface, it was issuing a variation instruction and
would therefore have to pay for the additional work done. Forest’s claim for this work amounts to
$17,118.86. Nakano submitted that the claim was inflated and should only amount to $8,473.80 arrived
at by using a rate of $0.99 per square metre. This rate was calculated using the same formula as
Forest did but replacing the skilled workers’ rate of $10 per hour with the general workers’
rate of $4.50 per hour plus 10% for profit. I accept this submission. Forest did not explain why
skilled labour had to be used for hacking. I therefore award Forest $8,473.80 for its hacking work. 2.3 Finishing of entrance canopy 51. Forest originally claimed that it had finished nine entrance canopies and was
entitled to be paid for this work as a variation. Nakano did not dispute that this was variation
work. It only disputed the number done. Forest subsequently conceded that it had done only six
canopies, as asserted by Nakano but continued to assert that it was entitled to more money than
Nakano was prepared to offer because it had not only plastered these canopies but had also laid
block walls, including corner beads and wire mesh, to the façade beam and walls of the entrance
canopies. Forest submitted that the rate for this item of variation work should not be based on the
external plastering work rate of $12.50 per square metre (which would mean that it would receive a
total of $5,318.25) but that it should be paid $2,970.48 for each canopy based on the materials
supplied and the labour charges involved. 52. Nakano submitted that Forest’s claim of $2,970.48 per canopy was wholly
arbitrary since its original claim was $5,000 per canopy. Further it had claimed the same amount for
each canopy even though these were of different sizes. Additionally, most of the work involved
plastering and, even if the rate was doubled, the claim should not exceed $10,700. 53. There was no evidence that the canopies were of different sizes. Mr Michael
Choo gave evidence as to how the cost of $2,970.48 per canopy is arrived at. This was not challenged
by Nakano in cross-examination. It is also true that Nakano’s calculation did not provide for the
cost of materials. There was no evidence to contradict Forest’s assertion that each canopy
required 24 man days of labour. This component accounted for most of the cost of construction.
Accordingly, I award Forest its full claim of $2,970.48 per canopy making a total of $17,822.88. 2.4 Grouting around door frames 54. This claim relates to grouting work done by Forest to the openings between
the door frames and block walls of the apartment units and of the lift lobbies. The total claim is
for $121,072 on the basis that Forest is entitled to receive $156 for each of the 696 apartment
units and $71 for each of the 126 lift lobby door frames. Nakano’s position is that grouting
around the doors was part of the negotiated price for internal plastering works. 55. During cross-examination, Mr Ling admitted that grouting around door frames
was not in Forest’s sub-contract. This was a significant concession since as far as Nakano was
concerned, the normal sequence of work was to install the block wall first and then install the
door. It was common ground that such a sequence of work would lead to gaps between the block wall
and the door which would then require grouting. Under cross-examination, counsel for Nakano got Mr
Shia to agree that installing the door first and then the wall (which would eliminate the need for
grouting) was the old fashioned way of proceeding. Since Nakano knew that the walls were to be
installed first and thus grouting would be required, it should have specified that the internal
plastering included such grouting. Its failure to insert such a term in the sub-contract is
significant. 56. I find in favour of Forest in this issue and award it $121,072. 2.4 Rectification of external walls 57. This claim for $273,275 relates to work which Forest did to rectify debonded
external plaster. It is Forest’s case that the debonded plaster resulted from Nakano’s fault and
was not due to its own poor workmanship. Nakano alleges the opposite and has counterclaimed for its
own cost of rectifying defective work. I will consider this issue when dealing with the
counterclaim. 2.5 Filling in of gaps between door jambs and reinforced concrete walls 58. Forest claims $11,616 for filling in the gaps between the lift door jambs and
the concrete lift shaft with lightweight blocks at block 19. Nakano’s position is that Forest did
not do this work. 59. Forest’s evidence in respect of this claim was given by Mr Koon. He stated
that, as far as he was aware, Nakano had instructed Forest’s site engineer, Mr Cai Yoa Zhong, to
commence these variation works. Further, some time in July 1999, he himself saw Forest’s workers
at block 19 filling in the gaps between the lift door jamb and the concrete lift shaft. Mr Cai
himself did not testify. 60. On the other hand, Nakano’s witness Mr Quek testified that he did not issue
any variation order to Forest to grout these gaps. He had considered getting Forest to do the job
but, as he had received poor report on their progress, he decided to award the work to another
sub-contractor, Kow Sang Woodworks. He stated that Nakano had told Kow Sang Woodworks to go ahead
and start the work in July 1999 and that a purchase order was issued for this purpose. The documents
attached to Mr Quek’s affidavit showed that Kow Sang Woodworks’ quotation for these works (which
probably extended to all the blocks and not simply to block 19 as it did not contain any reference
to any particular block) was dated 11 August 1999. Further, the purchase order issued by Nakano was
dated 12 August 1999 and specified the date of commencement of work as 16 August 1999. 61. It appears from the documents produced by Nakano that Kow Sang Woodworks was
only engaged in August 1999. No document has been produced to show that Kow Sang Woodworks did, and
was paid for, work at block 19. On the other hand, there is Mr Koon’s clear evidence that he saw
Forest’s workers doing such work at block 19 in July 1999 ie prior to the engagement of the other
contractor. I accept Forest’s submissions on this point and award it $11,616 as claimed. 2.6 Extra over thickness of internal wall plastering 62. The sub-contract provided that Forest would apply 8 mm of plaster to the
internal walls. The claim here arises from the contention that in fact Forest had to apply plaster
that was 10 mm thick on the areas of the block walls which were adjacent to the door frames in order
to ensure that the door frames merged with the block walls and did not jut out. This was because the
door frames were 120 mm wide whilst the block walls were 100 mm wide so that the door frames
protruded to the extent of 10 mm on either side of the adjacent block walls. An application of
plaster that was only 8 mm thick would not have completely eliminated the protrusion. 63. Nakano resisted Forest’s claim to be paid for the extra 2 mm of plaster
applied around the door frames. Various objections were put forward. The first was that whilst the
internal wall plastering commenced in September 1998, it was only on 1 July 1999 that Forest
mentioned that it had to provide an extra 2 mm of plaster adjacent to the door frames and that it
was incurring extra material costs. Further, the variation claim itself was only submitted in
January 2000. Secondly, Forest was trying to isolate the internal walls with door frames from the
rest of the internal walls despite the fact that the sub-contract did not make such a distinction.
Nakano’s position was that the 8 mm thickness specified in the sub-contract referred to an average
of 8 mm. There would have been areas where the plaster thickness was less than 8 mm and therefore as
long as the average thickness of the internal plaster was 8 mm, Forest was not entitled to make any
claim for over-thickness. Thirdly, Nakano submitted that there was no evidence that Forest did
plaster a 10 mm thickness throughout the wall. In any case, it was submitted that 2 mm was
negligible in terms of labour as well as the amount of plaster used when the sub-contract was
considered as a whole. 64. I do not find much merit in Nakano’s submissions. My opinion is that the 8
mm in the sub-contract referred to a fixed thickness and not an average thickness. This opinion is
based on a construction of the wording in the sub-contract. That is straight-forward with no
indication that a varying thickness was contemplated or submitted. Secondly, there is not much in
the point of delay in making the claim. Although the bill was not submitted until January 2000, Mr
Shia had, as early as November 1998, informed Mr Ling of the additional thickness required and that
this item of work was a variation. This was confirmed by the letter of 1 July 1999. 65. Thirdly, Forest did not try to draw any distinction between the block walls
adjacent to the doors and the rest of the block walls. All it contended was that it had to plaster a
thickness of 10 mm at either side of the block wall adjacent to the door frame in order to prevent
the door frame from protruding. Nakano’s evidence supported this. Mr SF Wong confirmed in court
that there was a defined area of 34,314 m² of block wall that required 10 mm of plaster and a
defined area of 83,314 m² of block wall that required 8 mm of plaster. Mr Wong also testified that
Nakano had told him that the areas with the door openings required plaster of 10 mm thickness
because of the protrusion of the door frame. Fourthly, the extra thickness of 2 mm was not
insignificant as contended by Nakano. Mr Wong admitted that in proportional terms 2 mm represented a
23% increase over the original thickness of 8 mm. 66. In my judgment, Forest is entitled to recover for the extra 2 mm of plaster
applied to 34,314m² of block wall. The question is as to the rate that it is entitled to charge. On
the basis of the agreed rate of $10.50 per m² to apply 8 mm of plaster, Forest calculated that it
cost them $13.125 per m² to apply 10 mm of plaster. It therefore claimed an extra $2.625 for each
square metre where an additional 2 mm of plaster had been applied. Nakano submitted that the rate
should not provide for additional labour as plastering an extra 2 mm is within reasonable tolerance
and did not involve any additional labour. It argued that, if at all, Forest would be entitled to
claim for additional cost of material only. It appears to me that whilst there must have been some
additional labour costs incurred in applying a thicker layer of plaster, it is not correct to obtain
this cost by simply taking a proportion of the original agreed rate of $10.50 per m². This is
because there would be some overlapping in the work done. There is already an agreed rate for
application of 10 mm thick plaster. This is $12.50 per m² ie the agreed figure for the external
plastering. I think this rate should also be applied to the areas of the internal walls which
received that thickness of plaster. On this basis, Forest should receive an extra $2 per m² for the
34,314m² of block walls which adjoined the door frames. I therefore award Forest $68,628 for this
work. 2.7 Plastering of separation walls 67. Forest claimed that the original scope of the internal plastering walls under
the sub-contract did not include plastering of the separation walls. Nakano subsequently instructed
Forest to do this work and Forest therefore claimed $129,856.50 for the same. 68. In its submissions, Nakano did not deal with liability for this work but only
with quantum. It pointed out that Forest was now claiming it should be paid at the rate of $13.50
per m² whereas previously it had claimed that the rate should be $15.50 per m². Nakano asserted
that whilst Forest had claimed that it had to apply, on the average, plaster that was 15 mm thick,
it had not produced any evidence that this had been done throughout all the separation walls. Nakano
submitted that since the separation walls were within the apartment units and not exposed to
weather, they should be considered as internal walls and the court should adopt the internal wall
plastering rate of $10.50 per m². 69. The evidence showed that originally Nakano had planned to skim coat the
separation walls. The subsequent decision to plaster them was made because it discovered that the
separation walls were not even and plastering was required to smoothen them out. Mr Shia’s
evidence was that when Nakano asked him to carry out this additional item of work, he made
investigations and was informed by his site supervisors that to adequately plaster these walls, an
average of 15 mm of plaster would be required. On 26 August 1999, Mr Shia put in a quotation for his
work at the rate of $15.50 per m². In the quotation the thickness of the plaster to be applied was
put as being 15 mm. Although Nakano did not formally accept this quotation, it must have been aware
of its existence when it instructed Forest to proceed with the work. Further, it must have been
aware that Forest was intending to apply 15 mm of plaster to the separation walls. In these
circumstances, I do not think it lies in Nakano’s mouth now to quibble about the reduction from
$15.50 per m² to $13.50 per m² or to suggest that the correct rate should be $10.50 per m² on the
basis that only 8 mm of plaster was required. Accordingly, I award Forest $129,856.50 for the 9,619
m² of separation walls plastered at the rate of $13.50 per m². 2.8 Amount of previous payments made 70. It is Forest’s case that the total amount paid to it by Nakano pursuant to
the various sub-contracts was the sum of $4,402,786.08. The full details of all receipts from Nakano
are contained in Appendix 5 to Mr Choo’s second affidavit. Nakano on the other hand asserts that
it had paid Forest $4,460,716.80. The difference between the two amounts is $57,930.72. Forest
submitted that Nakano had made a mistake in calculating the amount paid because it had wrongly
included payments which were due to Forest for another project. 71. Nakano submitted that this discrepancy was in fact due to Forest’s own
failure to properly account for the full sum of $165,747.63 which Nakano had paid to Forest pursuant
to BOTM cheque number 014148 dated 7 December 1999. This was Nakano’s first answer to the
calculation. 72. Appendix 5 to Mr Choo’s second affidavit shows the payments Forest received
in December 1999. It credited Nakano with paying it during that month the sum of $7,500.25 in
respect of the solid brick walls, $3,857 in respect of the steel lintels, $40,850 in respect of
tiling works, $87,762.90 in respect of the block works and external wall plastering, and $13,300 in
respect of the internal wall plastering. This table therefore shows that Forest acknowledged
receiving a total of $153,269.90 in December 1999. Thus, only $12,477.73 of the amount paid by
Nakano that month is unaccounted for in Forest’s accounts. At the most, therefore, Nakano has been
able to establish that Forest received $4,415,264.38 (ie $4,402,786.55 + $12,477.73). 73. Forest did not produce any documents establishing that any part of the
$165,747.63 paid by Nakano in December 1999 had been credited to the amounts due from Nakano on the
other project on which it had employed Forest. In the absence of such evidence, I have to hold that
the full $165,747.63 should have been credited to the amounts payable for the Woodsvale project.
Accordingly, Forest has not been able to establish that it received only $4,402,786.08. In my
judgment it received $4,415,264.38. 74. The other objection that Nakano raised to Forest’s account was that it did
not reflect 14 invoices and credit notes which were sent by Nakano to Forest between 28 July 1998
and 7 December 1999. These totalled $7,985.50 and comprised, in part, charges for repairs to
equipment allegedly damaged by Forest’s workers, and in part penalties imposed for various types
of damage inflicted and infringement of safety rules and insubordination. Nakano did not lead
evidence to establish that these invoices were validly raised and that Forest was legally liable to
pay them. Accordingly, I disregard this objection. 2.9 Outstanding balance due to Forest 75. By reason of the findings above, the balance amount due to Forest is
$1,670,177.96 (excluding 3% GST) derived as follows: ($) ($) (a) Agreed value of original sub-contract
works 5,100,896.76 (b) Agreed/Undisputed variation
works 34,501.40 (c) Variation works awarded: (i) extra thick external plaster 592,575.00 (ii) hacking keys 8,473.80 (iii) entrance canopies 17,822.88 (iv) grouting door frames 121,072.00 (v) filling in of gaps 11,616.00 (vi) extra thick internal
plaster 68,628.00 (vii) separation walls 129,856.50 Sub-total: 6,085,442.34 (d) Less previous payment: 4,415,264.38 Balance due: 1,670,177.96 Issues relating to wrongful termination and counterclaim 1. Forest’s claim for wrongful termination 76. On 13 January 2000, Nakano wrote a letter to Forest entitled ‘Termination
Warning’. The letter referred to various written reminders to Forest to re-plaster the hacked
areas in the external walls of the blocks and in particular to a letter dated 18 December 1999 which
enclosed lists of the locations to be re-plastered. It went on to note that despite this notice and
the further chance afforded to Forest to complete the re-plastering by 6 January 2000, it had failed
to do so. Further, instead of stepping up the work, the number of workers attending to the plaster
works on site had decreased. Forest’s letter of 7 January 2000 put it beyond doubt, according to
Nakano, that Forest had no intention of fulfilling its contractual obligations. The letter went on
to deal with the defective works and alleged that Forest was in default of its contractual
obligations. Nakano ended by giving Forest notice that it might terminate Forest’s employment. 77. The next day, 14 January, Nakano sent Forest a further letter. This was
entitled ‘Termination for Defaults’ (sic). It referred to the letter of 13 January and
stated that Nakano accepted Forest’s wrongful repudiation of its sub-contracts by terminating
Forest with immediate effect. Forest was asked to ensure that its remaining workers vacated the site
immediately. It was also notified that Nakano would be appointing alternative contractors to
complete the remaining sub-contract works, including rectification of the defective works. All costs
incurred would be charged to Forest. Nakano also reserved its right to claim damages from Forest. 78. The position taken by Forest throughout the trial was that its sub-contracts
for plastering works were prematurely and wrongfully terminated. As a result of this early
termination, Forest was unable to earn the profit in respect of work not performed which it would
have earned had the sub-contracts continued to their natural conclusion. Forest seeks compensation
of $7,264.24 for the wrongful termination. 2. Nakano’s position 79. Nakano’s position is that it was fully entitled to terminate the
sub-contracts and that Forest was the party in default. It claimed various amounts from Forest
arising from defective work, delays and the necessity of employing alternative contractors to
complete Forest’s work. The validity of some of these claims depends on the validity of the
termination notice. 80. In its re-re-re-amended defence and counterclaim filed on 6 September 2000,
Nakano cited condition 19 of its conditions of sub-contract. That condition is entitled ‘Termination
by Contractor’ and sets out the procedure whereby the contractor may send the sub-contractor a ‘termination
warning’ and, within two weeks thereafter, a notice of termination of the employment of the
sub-contractor. Nakano admitted that it had terminated Forest’s sub-contract on 14 January 2000
and stated that it would rely on the terms of the sub-contracts for their full intent and purposes. 81. Nakano went on to plead that Forest: (1) had failed and/or neglected to properly install the tiling works; (2) had failed to complete the solid brick wall sub-contract works; (3) had failed to complete its sub-contract for block wall and external wall
plastering by 30 October 1999 and that for internal wall plastering by 30 September 1999 and
thereby held up the rest of the main contract works; (4) had failed and/or neglected to properly install the block walls and the
internal and external wall plastering in that: (a) Forest’s inferior workmanship and lack of preparation of the substrate
surface resulted in a failure in the bonding within the plaster and between the plaster and the
substrate thereby causing hollows in the plaster; (b) despite repeated written and oral reminders by Nakano, Forest failed,
refused and/or neglected to rectify the defective plastering; (c) Forest was substantially behind its schedule of plastering works as at
July/August 1999; (d) having agreed to effect rectification works to the defective plaster wall
by hacking out the parts of the plaster that were hollow, Forest failed to make good the defects
but left substantial portions of the hacked areas un-replastered and, further, failed to attend
to other areas of defective plaster at all; and (e) despite promises to speed up the works, the number of workers sent by
Forest to the site progressively decreased. Nakano went on to plead that because of the matters that I have set out in para
81(4) above, it had sent a termination warning to Forest to terminate the sub-contracts relating to
the plastering of the external and internal walls in accordance with clause 19(2) of the conditions
of sub-contract. The termination notice was then served the next day. Alternatively, Nakano pleaded
that it would rely on those same matters to say that Forest had effectively repudiated the block
wall and external and internal wall plastering sub-contract works which repudiation was accepted on
or before 14 January 2000. 3. Legal position 82. As I have already held that the conditions of sub-contract appended by Nakano
to its purchase orders did not form part of the sub-contracts between Nakano and Forest, Nakano
cannot justify its termination of those sub-contracts on the basis of condition 19. Accordingly,
Nakano has to rely on its common law rights to justify the termination. Under general law, not every
breach of contract by one contracting party justifies the other (the innocent party) in terminating
the contract. Action to terminate can only be taken when the defaulting party has evinced an
intention to itself repudiate the contract. 83. As held by the Court of Appeal in San International Pte Ltd v Keppel
Engineering Pte Ltd [1998] 3 SLR 871, a defaulting party repudiates the contract when he
intimates by words or conduct that he is or would be unable to perform his obligations in some
material respect. Short of an express refusal or declaration, the test is to ascertain whether the
action or actions of the party in default are such as to lead a reasonable person to conclude that
he no longer intended to be bound by the provisions of the contract. However, even if the defaulting
party’s conduct does amount to a refusal to perform, it does not follow that the innocent party
would be entitled to terminate the contract unless the repudiation deprives the innocent party of
substantially the whole benefit which was the intention of the parties that the innocent party
should obtain from the obligations of the parties under the sub-contract then remaining unperformed.
The Court of Appeal opined that the materiality of the refusal must be weighed in the context of the
obligation then remaining unperformed and that this test was particularly applicable in the context
of construction contracts where progress payments are provided for works already completed so that
at the time of termination the parties are primarily concerned with the remaining unperformed
obligations and the impact on them of the particular breach. (See ¶ 25 and 26 of the judgment.) 4. Were the works delayed: (a) applicable completion dates 84. Whilst the pleadings, as summarised in ¶ 81 above, appeared to indicate that
Nakano would be relying on a whole host of allegations to justify terminating the sub-contracts, its
written submissions proceeded on narrower grounds. In closing, Nakano averred that Forest had
repudiated the plastering sub-contracts by its repeated failure to complete the works within the
agreed deadlines and by removing most of its skilled workers from the site some time towards the end
of December 1999 or in early January 2000 when there were still substantial areas where the
plastering work was incomplete. 85. The first sub-contract was for the block wall and external wall plastering
works. Nakano’s purchase order for this sub-contract provided that the works should commence on 17
August 1998 and be completed on 30 October 1999. In relation to the sub-contract for the internal
wall plastering, Nakano’s purchase order indicated a commencement date of 7 November 1998 and a
completion date of 30 September 1999. I should state here that I accept that the two dates indicated
as completion dates in the two purchase orders were the contractually agreed completion dates.
First, they were embodied in the purchase orders which were contractual documents and secondly, Mr
Shia did not complain at any time during the course of the project to Nakano that he had not agreed
to those dates. That lack of complaint must reflect an acceptance on his part. 86. Although both the internal and external plastering works were started before
the issue of the respective purchase orders, Forest was not able to complete these works by the
indicated dates. Nakano complained that despite being given final extensions to 15 November 1999
(for internal plastering works) and 15 December 1999 (for external plastering works), Forest had
failed to complete the work even by 14 January 2000, the date of termination. (b) Extent of works not completed on 14 January 2000 87. As at 14 January 2000, substantial areas of the external walls remained
unplastered or so Nakano alleged. According to Nakano’s evidence, the total external area to be
plastered was 85,565 m² of which Forest left 28,466 m² (or 31%) unplastered. As for the internal
areas, those not plastered by Forest as at 14 January 2000 were the penthouses of blocks 9A and 9B
(wholly unplastered); the penthouses of block 9C (partially plastered); the air-conditioner ledge
kerbs of blocks 9A, 9B, 9C and 11B; the access openings of blocks 9A and 9B; the type E1 & E2
penthouses of blocks 3 and 5; the staircase accesses of blocks 9A, 9B, 9C, 11A, 11B and 11C; certain
other small areas in block 19; and certain areas near the pipe shaft opening of all the blocks and
some other areas in the vicinity of the staircases of all the blocks. 88. There are some difficulties, however, with Nakano’s evidence relating to
the unplastered areas. First of all, at the time Nakano did not consider that 31% of the external
plastering had not been completed. At the beginning of December 1999, as shown by the minutes of a
site meeting, Nakano reported to the developer that 82.1% of the external plastering had been
completed. Mr Ling testified that this was the case but asserted this was an estimated figure. 89. The figure of 31% was derived from figures given in Mr SF Wong’s report.
According to his measurements, the total area of external walls requiring plastering amounted to
85,565 m². The report also stated that the area that had not been completed was 28,446 m². When Mr
Wong gave evidence, however, it appeared that the area of 28,446 m² had not been physically
measured by him. He had made only one site visit and that took place on 10 March 2000 by which time
the plastering work was in the course of completion. Mr Wong spent four hours on site but did not
take any actual measurements of the plastering works at that time. He testified that his
measurements of the quantities of the plaster were based, not on actual site measurements, but on
the drawings and plans supplied by Nakano. Further, he had depended on Nakano to identify to him the
areas of plastering which had been carried out by Forest. Mr Wong’s evidence was therefore not
primary evidence on the amount of work left undone by Forest. 90. There is also doubt about the correctness of the information given by Nakano
to Mr Wong. Presumably this information was similar to that contained in a list which Nakano gave to
Mr Law. That document listed all outstanding external plastering work and Mr Law then went round the
site with Nakano’s representatives in order to verify this list. The list was produced in court
and it is an impressive document running through some five pages with over 40 items on each page.
When Mr Law was cross-examined about it, however, he admitted that many of the items in the document
did not relate to distinct areas but related to the same area and the photographs taken reflected
this in that they did not always show distinct areas but often showed the same area from different
angles. The number of items therefore did not indicate directly how many areas were left
unplastered. 91. The onus lay on Nakano to prove the extent of the areas remaining unplastered
as at the termination of the sub-contract. It has not established to my satisfaction that 31% of the
external wall area remained unplastered. I accept, rather, the figure given to the owner in December
1999 as that was the contemporaneous estimate made and it must have been reasonably accurate since
the developer would have had consultants on site with the ability to carry out a physical check.
Further, there were no records kept by Mr Law on the incomplete internal plastering. As Forest
submitted, this was probably because the internal areas where the plaster work had not been
completed were not large enough to pose a problem for Nakano who had managed to complete the same by
the time Mr Law carried out his inspections between 31 January 2000 and 3 February 2000 and on 15
February 2000. (c) Was there delay? 92. It was common ground that the plastering of the external walls had to be
carried out in segments in accordance with the concrete casting of the external frame of each
apartment block which also proceeded in segments. The concrete form work was cast in segments of
four storeys per block each time. Once the casting of one segment of a block had been completed, the
Doka framework was removed and taken to the another block. Eight to 12 weeks would elapse between
the casting of one segment of a block and the return of the Doka for the casting of the next segment
of that block. The concrete had to harden and then BBR had to grind it and remove silt and
protrusions before Forest’s plastering work could commence. Nakano submitted that Forest had at
least six weeks to plaster the external walls of each segment before the Doka returned. It further
submitted that there were many instances when Forest started plastering a segment but failed, due to
the lack of manpower, to complete the same before the Doka returned. This lack of manpower led to
delays in the plastering since once the Doka returned, the hanging scaffoldings that Nakano had
supplied for the use of the plasterers had to be removed and plastering work on the segment had to
stop until the Doka left that block again. 93. Nakano’s witnesses asserted that Forest lacked manpower and it was this
lack rather than various other matters (eg a lack of scaffolding) put forward by Forest as excuses
that was the main cause of the slow progress of the plastering works. Nakano’s witnesses further
stated that they had sent chasers to Forest to increase the number of plasterers but that these were
ignored. Many of the segments had to be abandoned as a result of Forest’s slow progress. According
to Mr Ling and Mr Steven Lee, Nakano had provided about 78 sets of hanging scaffolding at the site
and this meant that three of the construction zones had 23 to 25 sets of scaffolding each intending
to cover the perimeter walls of two units of each segment. However, often the hanging scaffolding
was left unused. As Forest did not have enough workers, additional sets of scaffolding were not
brought in for the fourth zone. Instead, the sets on site were re-deployed among all zones from
about February 1999. 94. It was Nakano’s contention that for Forest to keep out with the sequence of
casting works and within Nakano’s schedule, it needed to have at least 17 workers per block
working on the 25 sets of hanging scaffolding provided over each segment. Since there were four
zones, Forest required about 68 plasterers to carry out plastering work simultaneously in all the
zones. Nakano pointed out that Forest had not supplied the total number of plasterers it had
available for the works. Instead, Mr Koon had stated that depending on the availability of the
working area provided by Nakano, a few groups of skilled workers, each group consisting of
approximately five skilled workers, would be engaged to carry out the work at the available
locations. In court, however, Mr Koon claimed that he would send two or three workers up per
scaffolding and that two of these would be skilled whilst the third would be a general worker. He
also claimed that Nakano had provided only about 16 sets of scaffolding for each segment. He then
claimed that he would need more than 20 plasterers for these 16 sets. On this basis, Forest would
have needed 80 plasterers to work in all four zones, 12 more than the figure estimated by Nakano. 95. Nakano submitted that Forest never had 80 plasterers for the external
plastering. Mr Koon, though unable to give even a rough estimate of the number of plasterers on
site, claimed that Forest had workers on every available scaffolding platform throughout the site
and that it was Nakano who did not have sufficient hanging platforms. On the other hand, the
evidence of Nakano’s foreman, Mr Lee, was that Forest had only four to five workers for the corner
beading and the level pegs for all four zones whilst it had eight to nine plasterers in each of the
four zones. Nakano had often asked Forest to increase its labour force. One such request was
documented in Nakano’s letter of 8 September 1999 which referred to a promise made by Mr Choo to
mobilise an additional 27 plasterers by 12 September 1999 to add to the then existing site workforce
of 32 plasterers. 96. Mr Koon asserted that during the course of the project, he had insured that
the number of workers engaged at the site was sufficient. Based on Forest’s records, an average of
64 skilled workers and 32 general workers were engaged per day. The general workers were engaged
directly by Forest whilst the skilled workers were either direct employees or obtained from labour
sub-contractors. Mr Koon also said that during the period September and November 1999 Forest had
engaged an average of 150 skilled workers and 32 general workers per day. A physical inspection of
the site was undertaken by Nakano towards the end of November 1999. At that point, Forest was found
to have 104 workers on site, a substantial number although somewhat below the 182 figure given by Mr
Koon for that period. 97. Mr Koon’s assertions were not, however, substantiated by documentation.
Forest does not seem to have kept complete and accurate records. Certain records showed that another
contractor had supplied Forest with 15 plasterers between August and November 1998. Other payroll
records produced by Forest apparently indicated that it employed 20 to 30 general workers from
October 1998 to January 1999 and thereafter, in addition to the general workers, 15 skilled workers.
No records of the actual number of plasterers working at the Woodsvale site were kept by Forest. Mr
Shia himself insisted that he had some Chinese plasterers but there are no records of the number of
these workers. Mr Shia was not able to remember the number of plasterers on site nor could he
explain the payroll records. Mr Koon himself was not able to say how many of the skilled workers who
were supplied to the site were plasterers as there were also skilled workers for block laying and
tiling. 98. On 10 October 1999, Nakano wrote to Forest. It expressed its regret that
despite several reminders regarding sub-standard quality of workmanship and work progress, Forest
had not taken Nakano’s instructions seriously. It further stated that since Forest had not been
able to meet Nakano’s schedule, it had extended Forest’s final completion dates for brick works
to 21 October 1999, for internal plastering to 15 November 1999 and for external plastering to 15
December 1999. Forest was informed that if it failed to improve its work performance and quality
immediately, Nakano would have no alternative but to accept Forest’s wrongful repudiation of the
contract by appointing alternative contractors and looking to Forest for all loss and expense. It
appears from this letter that Nakano was very frustrated with the progress of the work and was
beginning to build the case for termination. Mr Shia received this letter. He did not dispute its
contents. Mr Koon was aware of it as well. He asserted on the stand that at the time he received the
letter he thought that he should be able to finish the external plastering within two to three
months ie around mid December 1999. 99. In the event, by 14 January 2000, despite further agitation by Nakano and
several inspections of the site at which unfinished work was pointed out to Forest’s
representatives and promises were made to complete same, the internal and external plastering works
were not complete. In my opinion, Forest had been slow. The question is whether such delay justified
the action taken by Nakano to terminate the relevant sub-contracts. (d) Did delay justify termination? 100. At that time, Nakano had an obligation to deliver the completed project to
the developer by 6 May 2000. Its concern was that because of the slow progress of the plastering
works it would not be able to do so. This was because even after the plastering works had been
completed, there would be painting and external works to complete and the authorities would have to
inspect the project and issue the necessary approvals. Painting work scheduled for end December 1999
by Nakano had been held back due to the incomplete plaster works. 101. Nakano was also concerned because its foremen saw a significant decrease in
the number of plasterers in early January 2000. Mr Koan Ping Seng and Mr Lee recorded the number of
plasterers at the site on 7, 8, 9 and 10 January 2000 and these records showed that on those days,
there were only about 15 plasterers on site, roughly half the normal strength. 102. Whilst Nakano’s concern over the slowness of the work and the apparent
decrease in plasterers is understandable, that does not mean that it was justified in terminating
the sub-contracts. As held in Felton v Wharrie [1906] Hudson’s BC 4th ed Vol 2 p
398, delay to the works per se does not amount to repudiation unless it is of such magnitude and
character as to show that the contractor is either unable to proceed with the works or has no
intention of proceeding with them. At the time of termination, Nakano itself was not yet late under
the main contract and therefore the termination was an anticipatory one based on the concern that if
Forest continued to be slow it would inevitably delay Nakano’s own work. There was no clear
evidence of how allowing Forest to continue would have delayed Nakano’s own completion. As it was,
the rectification work carried out by Acolite after Forest was terminated was not completed until
around the end of May or June 2000 and, according to Mr Hattori, other works that had to be done
after this rectification work took a further two months. Thus, the termination itself caused delay
and there is no evidence that had Forest continued to work on the project it would not have been
able to complete at the same time that Acolite did. 103. Further, the slow progress of the plastering works was not entirely due to
default on the part of Forest. Nakano had a role to play in this as well. For one thing, Forest’s
plastering work was given a lower priority than the concreting works. This meant that any disruption
in BBR’s work resulted in serious disruption to Forest’s work and, secondly, resources that
Nakano were already short of were allocated first to BBR rather than to Forest. Mr Ling agreed that
priority in the use of resources was given to BBR to enable them to catch up with the casting
schedule and that the hanging platforms had been removed without regard as to whether Forest had
completed applying plaster so as to make way for the Doka form work to be brought back to enable BBR
to cast the next segment. 104. Secondly, a number of walls or parts thereof were not always ready for
plastering by Forest’s workers. The protrusions on the walls were not always trimmed, as admitted
by Mr Ling, as it was presumed that the plastering would hide the defective concrete. There was
evidence in the form of admissions by Nakano’s witnesses that at the time of termination some wall
surfaces had not been ground by BBR and/or Nakano and therefore were not ready for plastering work.
There were also delays in the inspection of the concrete work which in turn led to delays in
commencement of plastering work. Further, even at the date of termination the window sills had not
been installed in a number of blocks so that Forest was unable to plaster the areas around the
window sills. Mr Lee agreed that the minutes of a site meeting held at about that time showed that
window sills in blocks 9A, 9B, 11A and 11C had still to be hacked to enable installation of the
windows. 105. It was also significant that Nakano was rather haphazard in the
communication of its construction programme to its sub-contractors including Forest. In
evidence-in-chief Nakano had asserted that it had briefed the respective sub-contractors on the
sequence and timing of their respective works. Nakano’s witnesses alluded to a master programme.
During cross-examination Mr Hattori agreed that the plastering programme should have been agreed in
consultation with Forest as the sub-contractor responsible for carrying out the plastering work. He
also agreed that Forest was not consulted on the original master programme but asserted that there
was a revised programme and that during negotiations he had informed Forest that each segment of
concrete had to be plastered within four months. 106. Whatever Mr Hattori might have told Mr Shia during negotiations, there was
no evidence that Forest was consulted in relation to the revised master programme which was
submitted to the architect in February 1999. Mr Hattori’s testimony was that he had no idea
whether Mr Shia was consulted on this. When he was asked if he had told Mr Lee to consult Mr Shia,
his reply was that he could not recall whether he gave specific instruction to his staff members at
this time but they understood that when they needed to revise a schedule they were supposed to
consult particular contractors. Mr Lee when asked about this stated that he himself had not been
consulted about the revised schedule. If that was so, he could not have consulted Mr Shia about it. 107. It would appear therefore that the sequence and timing of the work were
planned by Nakano without any contribution from Forest. Instead, it was simply briefed on the
programme by Nakano. Mr Ling remembered that he had briefed Mr Shia on the schedule which he needed
to follow until the project was completed. By this he meant that he had told Mr Shia that the
plastering work had to be completed some time in July or August 1999 but he had not given him any
written schedule. When he was asked whether he would agree that most of the time Forest had been
given only a vague idea of when particular work had to be completed without any firm deadlines, Mr
Ling agreed after stating that he had verbally given Forest a schedule every day. 108. In any case, the master programme did not even properly mention or provide
for the plastering works. Mr Ling attempted, under questioning, to fit these works into the general
categories of ‘architectural works’ and, alternatively, ‘external wall finishing’. Both of
these, however, were much wider categories encompassing more areas of work. The plan, therefore,
failed to precisely indicate the schedule for the plastering works. This lack lends force to the
submission by Forest that there was in reality no plan and at best, decisions were taken on a weekly
basis as to where, how and when Forest should carry out its plastering work. To me it appears as if
there was a general idea as to what needed to be done within what time frame but without specific
deadlines within the general outline. Since the work was segmented and dependent on the progress of
the casting work it would have been very difficult to lay down specific deadlines. 109. Having considered the evidence as a whole, it appears that whilst Forest did
not work as fast as Nakano desired or as fast as it could have, there were various reasons for the
slow progress and among these were deficiencies on Nakano’s part as well. It was not all Forest’s
fault. Further, it was not at all clear at the time of termination that delays on the part of Forest
would have a devastating impact on Nakano’s work. Instead of resorting to termination, an object
which it seemed to have had in mind since October 1999, Nakano could have continued to chivvy Forest
to hurry up and also made a claim for damages against it if in fact the completion of the project
was delayed due to Forest’s slow speed. There was a submission made by Forest that because the
word ‘nil’ was entered against the heading ‘liquidated damages’ on Nakano’s purchase
order, Nakano would not be able to claim even general damages had Forest’s delay caused it to
suffer the same. It is not necessary for me to decide that point now but I should state that I find
it difficult to accept the proposition that simply because it was agreed that there should be no
liquidated damages clause, no damages at all could be claimed even if Forest was in default and its
delay caused loss to Nakano. 110. Accordingly I find that Nakano’s termination of the plastering
sub-contracts was wrongful. Forest would be entitled to damages for wrongful termination. It has
quantified these at $7,264.24 which it says is the profit it would have earned from the
sub-contracts if they had not been prematurely terminated. Details of this figure were set out in
appendices to the statement of claim. Nakano has not challenged this quantification. I therefore
award Forest $7,264.24 in damages. Nakano’s counterclaims 111. Nakano’s counterclaims are based primarily on Forest’s alleged failure
to complete the sub-contract works, on defects in the external and internal plastering works and
additional cost of rental for gondolas and platforms which resulted from Forest’s failure to
complete within schedule. As a result of Forest’s termination, Nakano had to appoint alternative
sub-contractors to complete the works and rectify Forest’s defective works. The particulars of
loss are as follows: (a) overpayment for external plastering sub-contract ($57,705.29); (b) Acolite’s invoices (ie $803,235 less back charges of $68,785); (c) Yu Bee’s invoices ($971,156.91); (d) Hai Hwa’s invoices (additional costs of labour and
materials)($85,327.89); (e) Kan Leong’s invoices (additional costs) ($98,875); (f) Wong Kam Thong’s charges for rectification of Forest’s defective tiling
works ($13,050); (g) Gondolas and climbing platforms ($415,146.62); and (h) Fines (not yet backcharged)($16,000). In the light of my finding on the issue of termination, some of the above claims
are no longer maintainable. I will deal with each claim in turn. (1) Overpayment for external wall plastering 112. In Nakano’s submissions, there is just one sentence on this claim. It
reads ‘Based on the agreed quantities for external wall plastering, the overpayment is $57,705.29’.
There is insufficient material on this submission for me to accept it. Further, even if there was an
overpayment of $57,705.29 in respect of the plastering, all payments made by Nakano to Forest have
now been taken into account in the calculation of what is due from Nakano to Forest as shown in ¶
75. This claim is therefore not allowed. (2) Acolite’s invoices ie payment for rectification of defective plaster 113. Nakano submitted that in relation to this claim, the two issues that arose
were (i) whether the defects found in the plaster were the result of Forest’s failure to follow
manufacturer’s specifications in relation to the application of Smartplas, its poor supervision of
workers and poor workmanship and (ii) if so, what should be the quantum of damages. 114. For the purposes of determining the reason why such a large portion of the
applied plaster debonded, both Forest and Nakano appointed experts to investigate and report. These
were Mr Kenneth Hugh Jones and Mr CW Wong. (a) Evidence of Mr Wong Chung Wan 115. Mr Wong is a qualified civil and structure engineer who holds a Masters
degree in Building Science. He is presently head of the Construction Technology Division and General
Manager of SETSCO Services (M) Sdn Bhd. SETSCO’s investigation was commissioned on 1 March 2000.
Mr Wong inspected the site physically on 6 March 2000. On the external facades inspection was made
visually from the ground level and internally some of the units and staircases were inspected.
Locations were selected for extraction of samples for laboratory analysis. Fourteen samples were
taken altogether, seven from external areas and seven from internal areas. In both cases, samples
were extracted from sound areas, areas with hollow sounding and areas with cracks accompanied by
hollow sounding. As there was no specific pattern of distribution of the defects, the samples were
extracted randomly from accessible areas. 116. Mr Wong took the samples back to his laboratory and subjected them to
various tests. One of these tests was a Petrographic examination to determine the plaster’s
microstructure and composition. He also prepared samples of plaster from fresh bags of Smartplas.
Two samples were prepared and applied in accordance with the manufacturer’s recommendation. The
plaster was applied onto a G40 concrete substrate and the control samples were then subjected to the
same sort of Petrographic examination. 117. In his report, Mr Wong stated that during the initial walk-around
inspection, no clear pattern of distribution of the failure in the plaster could be detected. The
failure appeared random, similar to the mode seen from photographs of the site which had previously
been furnished to him by Nakano. These photographs indicated that the failure was widespread. As a
result, subsequent detailed inspection was confined to blocks 5, 7, 9 and 17 which showed similar
modes of distress. Unfortunately, due to access constraints, the physical inspection was confined to
the lower storeys and no close up inspection of the external façade of the upper storeys was
carried out. 118. In relation to internal plaster works, the visual inspection was made at the
reinforced concrete staircase shaft. It was observed that: (1) hollow sounding areas were often accompanied by pattern-cracks (0.2 to 0.5
mm in width); (2) detachment (falling off) of plaster had physically occurred in considerable
areas and bulging of debonded plaster was evident; (3) web-like pattern cracks were found even in areas without hollow sounding; (4) thickness of plaster varied widely from 9 to 20 mm; (5) debonding failure occurred mostly between the plaster and the concrete
substrate and to a lesser extent, between the different layers of the plaster. 119. Having completed the visual inspection of the site and the laboratory
analysis of both the samples taken from the site and the control samples made up and applied in the
laboratory, Mr Wong came to the following conclusions: ‘(1) the failures observed on site appeared to be widespread, with no
apparent consistent pattern or distribution. On concrete substrate, ie, external walls and
staircase walls, the failure manifested as debonding of the plaster and was often accompanied by
cracks. These cracks appeared largely as random pattern cracking, similar to shrinkage. The mode
of delamination was mostly failure between the plaster and concrete substrate and debonding
between layers of plaster. Bulging of the debonded plaster was also evident. (2) The appearance of random pattern cracks on the plaster indicates those that
are usually caused by shrinkage. This is likely due to inherently high shrinkage of the plaster
or/and cracking due to shrinkage. Higher shrinkage is usually expected for the mixes that have
higher amount of water than the amount recommended. Too much water in the mix causes a reduction
in strength of the plaster, higher shrinkage of the plaster and would have contributed to the
debonding of the plaster from the substrate or between layers. (3) The adhesion bond strength of both the control samples exceeded the minimum
requirements spelt out in the HDB’s specification. This is despite the slight deviation in the
mode of application for control #2. (4) Petrographic examination of plasters extracted from site and compared
against laboratory simulated samples revealed that: (i) signs of efflorescence or cement laitance were detected along the
interface between the base and final coat. Such deposits are caused by the migration of the
plaster constituents from within the plaster mix to the surface of the coat. Such a migration
would not occur if the right mix of powder and water was adhered to. In any case, these deposits
should have been removed/cleaned before plastering, as it will inhibit adhesion. (ii) where debonding was reported, there was significant amount of voids
along the plaster and concrete interface. This indicates the lack of a tight application of the
base coat to the concrete substrate. The simulated samples showed very good contact between the
base coat and concrete substrate with small amount of voids along the interface. The lack of the
tight base coat would have resulted in poor adhesion between the plaster and concrete substrate; (iii) over combing of the base coat was also detected resulting in cutting
through of the base coat into the concrete surface. This contravened the recommended practice as
highlighted in the technical brochure; (iv) large gaps and voids were found between the final and base coat,
apparently due to insufficient pressure being applied why laying the final coat or poor
workability of the plaster at the time of application. This has resulted in poor contact between
the two layers and hence weak bonding. It is therefore not surprising to see failure between the
base coat and final coat of the plaster on site. (v) neither spatterdash nor key coat was detected, though recommended in the
technical brochure. Similar recommendation is also given in BS 5262, which is also referred to
in the technical brochure; (vi) large variations in thickness of each layer were evident and in several
occasions, the total thickness of the plaster exceeded the maximum of 20 mm recommended. In
addition, the thickness of the final coat(s) generally exceeded that allowed by the
manufacturer. Thickness of the samples extracted from areas without defects seemed to comply
with the limit given by the manufacturer. A final coat that is too thick causes detachment of
the plaster.’ 120. It can be seen from the above analysis that Mr Wong’s main conclusion was
that the debonding was due, in large part, to poor workmanship on the part of the plasterers. This
manifested itself in too high a proportion of water being used in the mixing of the Smartplas, a
lack of tight application of the base coat to the concrete substrate, over combing of the base coat,
insufficient pressure being applied when laying the final coat, poor workability of the plaster at
the time of application and lack of bonding agents such as spatterdash. (b) Evidence of Mr Kenneth Hugh Jones 121. Mr Jones has 25 years experience as a professional building surveyor engaged
in the assessment and appraisal of residential, commercial and industrial buildings. He is a fellow
of the Chartered Institute of Building and of the Architecture and Surveying Institute and a member
of the Australian Institute of Building Surveyors and the Australian Institute of Building. Prior to
settling in Singapore in 1991, he provided building surveying services and technology services in
Australia, the Middle East and the United Kingdom. According to his c.v., Mr Jones has extensive
expertise in the diagnosis of building defects and the preparation of effective solutions to
building problems, based upon extensive practical experience and an in-depth technical knowledge
gained from 43 years of study and research. 122. At the beginning of 2000, Mr Jones’ company, Robinson Jones Associates Pte
Ltd, was instructed by Forest to carry out a survey inspection and necessary investigations in order
to establish the cause and reasons for localised bond failures between reinforced concrete walls and
applied external plaster at the Woodsvale project. Mr Jones carried out a site inspection on 1
January 2000. This comprised a visual examination of the exposed reinforced concrete walls, the
applied plaster and areas of the substrate where the debonded plaster was being replaced. No opening
up of the fabric or the structure of the building was carried out. Three further visits were made to
the perimeter of the site for the purpose of taking digital and infra-red photographs. 123. Mr Jones’ investigations included examination of digital and infra-red
photographs of the plastered and unplastered areas of the reinforced concrete walls, a study of the
technical specifications of the premix plaster form work system and the pin-fixing system carried
out by Acolite. He also examined samples of cured plaster removed from the walls and did
calculations to quantify the actual average thickness of applied plaster. 124. On conclusion of his investigations, Mr Jones opined that the cause and the
reason for the bond failure of the localised areas of the plaster resulted from some or all of the
following factors: ‘(a) the reinforced concrete walls, which form the substrate to which the
subject plaster has been applied, were constructed using system formwork with smooth forms, which
produce a totally smooth finish; (b) despite the use of smooth forms, no measures were taken to provide an
appropriate keyed surface by scabling the surface of the concrete, or wire brushing upon removal
of the formwork; (c) the placement of the concrete was erratic and had been over vibrated at
some locations, resulting in a layer of weak material with a high silt content on the face of the
concrete; (d) the forms were not raised and set in a regular and even vertical plane,
resulting in a need for significant variations in plaster thickness. This in turn has resulted in
differences in the rate of thermal movement to the cured plaster and uneven stress at the bond
joint between the plaster and concrete. (e) it is possible that mould oil, or other release agents had been applied to
the face of the forms and that the surface of the concrete could contain traces of these
chemicals.’ In summary, Mr Jones’ opinion was that rather than the defects in the plaster
having arisen from bad workmanship, they had been caused by the nature of the concrete walls and
deficiencies in the treatment, placement and vibration in the concrete. These were matters for which
Nakano rather than Forest would be responsible. (c) Discussion and findings 125. Dealing first with Mr Jones’ opinion, there are some difficulties with
accepting all of his conclusions. The first possible cause of bond failure put forward by him was
that the reinforced concrete walls were constructed using system form-work with smooth forms which
produced a totally smooth finish. Mr Jones suggested that indented form-work should have been used
when the concrete was cast. In cross-examination, however, he admitted that he had never seen this
type of form-work used in Singapore. That being the case, there must be means of insuring that
despite the use of system form-work like the Doka, plaster would adhere to the resulting smooth
concrete. 126. Whilst the smooth surface may have contributed to the difficulties initially
experienced in achieving a bond between the plaster and the external walls, it cannot have been the
only or main cause of the debonding. This is because when the debonding first became obvious, Nakano
instructed Forest to hack keys onto the concrete surface and also to use a bonding agent. Despite
these steps delamination continued to occur thus disclosing that there were other reasons for the
defects. It would also be noted that when Mr Wong made up a sample of plaster in his laboratory and
applied it to a slightly roughened concrete surface, he found the degree of adhesion of the plaster
to the concrete to be good. This indicates that properly mixed plaster would adhere to the concrete
once keys had been hacked into it. 127. The next opinion was that there was a high silt content on the face of the
concrete because it had been over-vibrated resulting in a layer of weak material with a high silt
content on the face of the concrete. This layer would inhibit the cementitious bond from coming into
being between the plaster and the concrete substrate. Mr Jones opined that this layer of silt was
the main cause of the debonding of both the internal and the external plaster. He stated that the
appearance of the concrete, particularly its light grey colour and the smoothness of its surface
indicated that high levels of fines made up of silt and other fine particles had migrated to the
face of the forms during placing and compaction of the concrete. 128. During re-examination of Mr Jones, it turned out that he had not seen the
surface of the concrete himself. He had simply relied on photographs of the substrate for his
analysis of what the appearance of the concrete meant. Thus, his evidence was speculative rather
than based on physical examination. On the other hand, Mr Wong had conducted a microscopic
examination of samples of all the various layers of the reinforced concrete wall, including the
substrate. During cross-examination, he stated that his investigations, both by way of visual
inspection on site and by way of laboratory examinations of extracted samples, did not reveal silt
on the surface of the substrate. He disagreed that the photographs showed obvious levels of silt on
the concrete. He said it was very difficult to tell from photographs whether the concrete surface
was covered by fines or not because the photographs showed concrete surfaces that had the same
appearance as most concrete surfaces. 129. Further, even if there had been a layer of fines or silt at the surface of
the concrete substrate, this layer would have been removed by grinding. Mr Jones agreed that
grinding the surface of the substrate would remove all the silt. The evidence given by Nakano’s
witnesses was that grinding regularly took place and the whole surface of the wall was ground and
not just the protruding areas. No doubt there were times when, as alleged by Forest’s witnesses,
the grinding was slow or incomplete but there is no evidence that this was a widespread phenomenon
or that the areas of debonded plaster were co-extensive with the areas which were not ground by
Nakano or BBR. 130. Mr Jones’ third observation was that the forms had not been raised and set
in a regular and even vertical plane resulting in a need for significant variation in plaster
thickness. Mr Jones had come to certain conclusions on the thickness of the plaster applied. He had
seen certain areas on the walls where plaster had been hacked off at the time of his inspection and
in these cases the thickness of the plaster had ranged from 10 mm to 30 mm. Further samples of
removed plaster were delivered to his office subsequently and these were between 19 mm to 49 mm
thick. 131. Mr Jones, however, was not aware whether these plaster samples were taken
from walls that allegedly had a verticality problem or exactly how much the alleged deviation from
verticality was. His evidence was that he did not check the verticality of the walls himself. His
conclusion that the walls were not raised and set in a regular and even vertical plane was based
mainly on his observations of the hacking of a significant number of windows. During
cross-examination, however, he agreed that the alignment of the window reveals had no effect
whatsoever on the verticality of the form-work. 132. Mr Jones bolstered his opinion by suggesting that a possible reason for the
alleged misalignment of the form-work was the combination of the system form-work with traditional
form-work construction methods. During cross-examination, he admitted that this was his own
suggestion and did not come from the suppliers of the Doka. He also admitted that the possibility
was mere speculation and that he did not have any evidence of such a combination having taken place
in this case. He further testified that he was not familiar with the Doka form-work and that he was
basing his comments on it purely on the brochures. 133. Mr Jones was not able to support his theory that the walls were not set in a
vertical plane. No doubt I have found that there were deviations from verticality as shown by Nakano’s
own records, but the extent of these deviations was not such as to be significantly outside of the
permitted deviations required by the Singapore Code of Practice CP 23 as opined by Mr Jones. The
verticality check results taken by Nakano were passed by the structural engineer as being within the
permissible tolerances. Mr Jones was not aware of this position. It appeared to me that his view of
the verticality problems was an exaggerated one. In any case, the significance of the verticality
problems lay in Mr Jones’ view that varying thicknesses of plaster contributed to debonding. This
view was severely undermined in cross-examination. 134. Mr Jones had stated that the variations in the plaster thickness had
resulted in differences in the rate of thermal movement to the cured plaster and uneven stress
between the plaster and the concrete. No calculations were given in support of this theory but only
a sketch showing how the thickness of the plaster varied over the height of the wall. His theory was
in areas of thicker rendering, the thicker mast of the plaster would expand linearly less than the
thinner mast of plaster. Therefore, at the point where the thickness changed, the thinner plaster
would exert a compressive force against the thicker plaster which would cause the thinner plaster to
move outwards and away from the wall, thereby debonding. 135. During cross-examination, Mr Jones agreed that the formula for linear
expansion of materials is the multiplication of the length of the material with the thermal
coefficient of the material and the difference in temperature. It was put to Mr Jones that this
formula did not take into account the thickness of the material and thus for a given material of
similar length but of any given thickness, the amount of linear expansion would be the same for a
given range of temperature. Mr Jones stuck to his theory but was unable to cite an alternative
formula to account the thickness of the plaster. Thus, as Nakano submitted, there did not seem to be
a scientific basis for Mr Jones’ thermal expansion theory. It should also be noted that Mr Jones
eventually admitted that his thermal expansion theory would not cause debonding to occur if the
plaster had properly adhered to the wall in the first place. 136. In any event, as Mr Jones admitted, since the internal walls of the
buildings were not as exposed to the normal temperature changes as were the external walls, the
large scale debonding of plaster that occurred in the internal areas was not due to thermal
expansion. Under questioning by me, he also admitted that even externally, if everything else had
been in order, the plaster would not have been debonded simply because of thermal movement. 137. In the course of his report, Mr Jones opined that vibrations emanating from
concrete work on the higher storeys of a block could be transmitted to the completed sections of the
walls below and that this vibration ‘would to some extent disturb the bond between the newly
applied plaster and the RC walls’. In his conclusions, however, he did not include vibration as a
cause of debonding. In view of this, I do not think I need to spend much time on this theory. I note
that Mr Wong had disagreed with Mr Jones’ opinion on the basis that most of the vibrations
generated by the poker vibrator used to compact the wet cement would have been absorbed by the
cement itself. Even if the vibrator had come into contact with the form-work or the steel
reinforcement, the vibrations would still be absorbed by the fresh concrete and the amount of
vibration transferred down to the lower walls would be minimal. Further, for some blocks in the
project, the plaster was applied to the external walls only after all concreting work to those
blocks had been completed. Yet, debonding of the plaster on these walls still occurred. This
evidence makes it highly improbable that vibration was a contributing factor to debonding. 138. The final possible reason for the debonding given by Mr Jones was that ‘mould
oil, or other release agents had been applied to the face of the forms and that the surface of the
concrete could contain traces of these chemicals’. This appears to me to be pure speculation since
no tests on the concrete were carried out to ascertain the presence of these chemicals. Further, Mr
Jones agreed in cross-examination that grinding and washing the walls before plastering would remove
these chemicals. As I have stated earlier, grinding works were regularly carried out. Further,
Forest’s evidence was that it would wet the walls before applying the plaster. 139. Turning to Mr Wong’s reasons for debonding, as Nakano pointed out in its
submissions, there was evidence which supported the theories that the plaster had not been properly
mixed and properly applied by Forest’s workers. First of all, it was clear that neither Mr Shia
nor his supervisors had ever read the specifications for Smartplas or the instructions as to how
mixing of the material with water should take place. It is not surprising that their mixing process
was not that recommended by the Smartplas manufacturer and whilst from the evidence the proportions
of Smartplas and water mixed were roughly correct, it appeared that there was no system in the
mixing and that what was done was done without any reference to the manufacturer’s instructions.
Further, the mixing of plaster was not always carried out under supervision. 140. My impression of Forest’s supervisors were that they were rather rough and
ready and also complacent. They were sure that what they were doing was correct. They relied on
previous experience and did not take the trouble to study manufacturer’s instructions whether in
relation to the use of Smartplas or to the use of the bonding agent Hydroment 476 Crete (‘Hydroment’).
The latter was added directly into the plaster mix which was a mode of use which was only prescribed
when the plaster was intended to be applied as a thin-set mortar. For the Hydroment to be used as a
bonding agent, it should have been mixed with type 1 Portland cement to form a slurry bond coat. Mr
Kumar and Mr Koon also gave contradictory evidence on the way that the Hydroment was used and the
amount of water used in the mix at that time. I accept Nakano’s submission in this regard that
Forest had acted in contravention of the instructions set out in the specifications to the Hydroment
by (a) adding water into the Hydroment; (b) using Smartplas instead of Portland cement and (c) by
mixing one part of Hydroment with two parts of Smartplas and water. 141. I find Mr Wong’s evidence persuasive. His opinion was clear and was not
adversely affected during cross-examination. He was able to explain his methodology well. His
findings indicate that more water was added to the plaster mix than was recommended by the
manufacturer’s of Smartplas and that this was the cause of the high shrinkage of plaster that led
to cracking and debonding. I also accept his evidence that a large number of air voids were found in
the site plaster and this was contributed to by various types of poor workmanship on the part of
Forest’s workers. I note that the number of samples taken by Mr Wong was small. In relation to the
cause of the defective plaster, I accept his explanation that these samples can be regarded as
representative although the debonding occurred over a large area because the failure areas showed a
similar manner of distress and the failure appeared random. 142. Forest, in its reply submissions, criticised Mr Wong’s conclusion that
there was too much water in the plaster mix on the basis that in the original report, this
conclusion was based on the ‘appearance of random cracks’ only. The laboratory findings were
raised only at the trial. Forest submitted that that was a surprising, if not irregular, way to
treat findings made and that there was no reason why the same should not be documented if they were
valid. Whilst it would have been better for the laboratory findings to have been mentioned in the
report, this does not mean that I should disregard the evidence entirely. As stated, I found Mr Wong
to be a professional and reliable witness and in my view, the quibble raised by Forest could not
detract from the essential truthfulness of the evidence. 143. Forest also raised objections to general inferences being derived from a
small number of samples. I have already dealt with that. It then went on to submit that the
conclusion was arrived at by a comparison of what Forest had applied with a control sample produced
under ideal and perfect conditions. This, Forest submitted, was grossly unsatisfactory. I do not see
much force in this submission. Forest was in effect saying that on site it is not possible to mix
and apply plaster properly. Surely, this cannot be the case. It is always possible to follow the
manufacturer’s instructions as to mixing if one is aware of them (which Forest was not) and as for
application, the samples which Mr Wong examined were taken from the lowest storeys of the blocks and
thus, Forest should have had no problem in properly applying the plaster to those areas. No hanging
platforms or gondolas would have been required for such application. Thus, the conditions in which
the applications were made would not have varied significantly from laboratory conditions. 144. Referring to the samples extracted from external areas, Forest noted that Mr
Wong’s evidence was that for plaster taken from areas without hollows, bonding between the plaster
and the concrete substrate appeared good and well applied with few amounts of void along the plaster
surface. Adhesion between the different layers of plaster also appeared good. From the samples
extracted from debonded areas, there was a significant number of voids across the cross section of
the plaster. Forest concluded that for areas where there was no debonding, the comments were
favourable to it. Forest therefore submitted that it must be concluded that its workmanship was, on
the whole, good. To say otherwise would lead to the ‘anomalous conclusion’ that Forest’s
workmanship was bad for debonded areas, but good for areas where the plaster did not debond. I do
not follow the logic of that submission. In my view, a conclusion that Forest’s workmanship varied
from good to bad is not ipso facto an anomalous one. It is the explanation why the debonding was not
wholesale. If the condition of the concrete was the reason for the debonding, then one would have
expected wholesale debonding as the concrete was the same throughout the project. The very fact that
debonding took place at random is an indication that it was due to poor workmanship rather than the
inherent condition of the substrate. 145. Forest had no control over the quality of the plasterers in that many of
them were not direct employees of Forest but were furnished by labour sub-contractors. It does not
seem to have insisted that all of these had proper qualifications since it could only produce
documents establishing the plastering qualifications of about 15 workers. I was not very impressed
either with the technical skills of the Forest supervisors. They appeared somewhat slap-dash and,
for plastering work, to rely more on experience than proper training. Mr Koon for example possessed
a Skills Evaluation Certificate in Electrical Wiring and Lifting Supervisor Safety. He had no
qualifications in the installation of block walls, brick walls, tiling or plastering works. Whilst
he had had some experience previously in supervising plastering works, the Woodsvale development was
the first time in which he had worked in a project which had a number of multi-storey blocks. Yet Mr
Koon was the main supervisor. 146. As for Mr Kumar, he had had no formal training in plastering work but had
supervised plastering and tiling works in more than five projects in Malaysia. His Malaysian
projects had, however, involved shop-houses, factories and terrace houses, not high-rise blocks. In
two of those projects, he had used a premix plastering cement that, according to the product
brochure, could be mixed either by hand or in a drum. He did not read the Smartplas brochure. All he
knew about mixing it is what Mr Koon had told him and Mr Koon’s instructions related only to the
proportion of water to be used and not to the method of mixing. I was also amazed by the fact that
Mr Shia could describe Mr Choo as a supervisor when it was clear that the latter had neither the
experience nor the training nor the time to carry out any supervision of the plasterers. 147. Having considered the evidence as a whole, I am satisfied that the defects
in the plastering work were the result of poor workmanship on the part of Forest. This being the
case Forest had to rectify the defects on its own account and cannot claim any money for
rectification work. Its claim for $273,275 for such work mentioned in no. 54 is therefore
disallowed. (d) What damages can Nakano recover? 148. Nakano accepted that the conventional method of rectification of plaster
defects was to hack out the defective plaster and then re-plaster the area properly. This method of
rectification is also that prescribed by British Standards. In this case, however, Nakano did not
resort to that method in order to rectify most of the defective plaster. Instead, it appointed
Acolite to rectify the debonded plaster by using the pin injection method. Its claim against Forest
for the sum of $734,450 represents the total charged to it by Acolite ($803,235) less the amount
which it claimed from Acolite as ‘backcharges’ ($68,785). 149. Nakano argued that after terminating Forest’s employment, it had to
complete the rectification and outstanding plaster works as soon as possible in order to avoid
paying the owners of the project liquidated damages of $35,000 per day. It argued that had it
employed conventional plasterers, the rectification work would have taken much longer. Further, no
third party sub-contractor was willing to quote for hacking and re-plastering of defective plaster
works. In this respect, Nakano referred to efforts that it had made to obtain quotes from third
party contractors and the fact that for those portions of the defective areas that were rectified by
conventional means the rectification works were carried out by workers supplied by Yu Bee
contractors on a daily-rated basis. 150. Forest on the other hand submitted that it had never agreed to the
employment of Acolite as the rectifying contractor. Further, Nakano did not exercise any supervision
or control over Acolite’s work. There was no control over the number of pins they put in and no
proper explanation was ever given why small areas of debonding required the large number of pins
inserted. No proper negotiations were carried out and Acolite’s quotation was accepted with
question. Further, the original method statement by Acolite required nine pins per metre square.
Subsequently, however, this was changed to 36 pins (at $5 per pin) per metre square. Mr Hattori’s
explanation for the change was that it was required by the architect. Forest complained that the
architect was not called to verify this nor was there any documentary evidence substantiating the
explanation. I find Mr Hattori’s explanation for the change in the number of pins credible. As
Nakano had to pay Acolite’s bills first with no guarantee of being able to recover any part of the
same from Forest, it would be eager to ensure that the pin injection costs would be as low as
possible. Quadrupling the number of the pins and thereby quadrupling the costs cannot have been
Nakano’s idea. I am satisfied that it would not have done this without a positive direction from
the architect. 151. Forest further submitted that it was completely unreasonable for Nakano to
employ Acolite and incur rectification costs of $803,235 for an area of approximately 4,462 m² of
plaster (calculated on the basis that with 36 pins being inserted per square metre, the cost per
square metre was $180) when Forest had charged $810,106.25 (based on the original rate without
inclusion of the charges for extra-thickness) for 64,828.5 m² of external wall plastered. 152. In this respect, Forest as the party in breach of its contractual obligation
to provide proper workmanship in the application of the plaster cannot insist on the rectification
work being done in any particular manner and at any particular price. As long as Nakano had acted
reasonably in taking the steps that it did to rectify the bad workmanship, Forest would have to pay
for the same even though the cost is on the high side. In this case, the situation was that Forest
was having difficulty doing both the rectification work and the plastering work. That was why Nakano
brought Acolite in in the first place. Although Mr Shia says that he did not agree to Acolite being
brought in, it seems clear that he did not seriously object to their participation until he received
their third bill and found out just how expensive this method of rectification could be. At that
stage, he wrote to Nakano telling them that he had then obtained sufficient labour to carry out
rectification works and asking them to stop Acolite’s participation. Nakano acceded to his request
for a few weeks but brought Acolite on site again when it was clear that Forest was lagging behind
in the rectification works. 153. The evidence also established to my satisfaction that Nakano had difficulty
in finding a conventional plasterer to carry out the rectification works after it terminated Forest.
Its explanation for these difficulties was a reasonable and credible one. No one wanted the onerous
and time consuming task of rectifying someone else’s defects. In the end, it only managed to
obtain plasterers from Yu Bee to rectify the defective internal plastering on a daily basis. The job
had to be done quickly as Nakano was facing time pressure by reason of the looming deadline for
completion of the project. It was therefore reasonable for Nakano to continue to employ Acolite on
this job although their costs were high. On the question of cost, it must also be observed that in
any case, Nakano would not have been able to employ plasterers to do the rectification work on the
basis of any rate close to that originally charged by Forest. Forest itself charged differently for
rectification work. Its bill for the rectification work it did was calculated on the basis of number
of workers supplied over a four and a half month period and the cost of the materials. This bill
came up to $300,000. Yu Bee’s charges for its supply of daily rated plasterers also shows that it
is expensive to employ plasterers to do conventional plastering when rectification work is involved. 154. In the circumstances, Nakano is entitled to recover from Forest the sum of
$734,450 which it paid to Acolite and I award it the same. (3) Yu Bee’s invoices 155. Nakano sought to claim from Forest the amount of $971,156.91 which it paid
Yu Bee. In its submissions, it stated that it had had difficulty in engaging third party contractors
to take over Forest’s incomplete works as well as rectification works. Yu Bee was only prepared to
provide day workers to do plaster works under the supervision of Nakano’s site supervisors. Nakano
had no choice but to accept this offer although it meant that Nakano would end up assuming the risk
of bad workmanship on the part of Yu Bee’s workers. Yu Bee’s workers were used primarily to
rectify the defects in the plastering works and some touch up on the external defects. 156. Forest submitted that Nakano’s total counterclaim for $2,472,943.92
covering both defective and incomplete works had not been sufficiently broken down to disclose the
basis of the various items constituting the counterclaim. In particular, the item of claim based on
Yu Bee’s work cut across both categories but was expressed in the single amount of $971,156.91,
apparently for day works. In the end it was not clear whether Yu Bee and the other contractors were
charging for work done to complete work left undone or to rectify defects. 157. I agree with the submission made by Forest that there are two distinct heads
of counterclaim that Nakano must address, namely damages flowing from (a) the alleged failure to
complete and (b) alleged defective work. This distinction is particularly important because I have
found in Forest’s favour in relation to the termination for the alleged failure to complete whilst
I have found in Nakano’s favour in relation to defective works. Since I have found that Nakano
should not have terminated Forest’s employment, it cannot recover the cost of employing other
contractors to complete the work left undone at the time of such termination. It is, however,
entitled to recover the cost of rectifying Forest’s defective works. As Forest further submitted,
the onus is on Nakano to satisfy the court how much it incurred in respect of rectification work and
that the overall amounts that it claimed were properly apportioned between the incomplete work and
the rectification work. 158. Forest submitted that in relation to Yu Bee, Nakano had not properly
apportioned the sum of $971,156.91 between rectification works and completion of incomplete works.
An analysis of Yu Bee’s bills made by Forest showed that the total amount comprised $370,702.50
for external bricklaying, $44,091.89 for bricklaying and $556,437.51 for internal wall plastering.
Looking at Yu Bee’s bills, I could not see how Forest was able to distinguish between the
bricklaying and internal wall charges which together amounted to $600,454.41. As the rectification
of the external walls was done mainly by Acolite, I think the figure of $370,702.50 must have
related mostly, if not totally, to plastering of the incomplete areas by Yu Bee’s workers.
Therefore, it cannot be claimed. 159. In relation to the remaining amount, it was the evidence of Mr Zuraimi that
after Forest had been terminated he had inspected blocks 1 and 3 in order to identify hollows in the
internal plastering. Thereafter, day workers supplied by Yu Bee worked under his supervision to
rectify the defects in these blocks. The workers hacked and re-plastered hollow areas and also
re-plastered the hacked areas left behind by Forest. They also ‘made good’ uneven surfaces. The
rectification works were tedious and took about five months to complete. In addition, according to
Mr Ling, Yu Bee’s workers took over all the outstanding plastering of the internal walls.
According to him, these were extensive. His listing of the outstanding work is set out in ¶ 87
above. It is impossible for me to apportion the sum of $600,454.41 between the costs incurred for
rectifying defective plaster and those incurred for completing outstanding work. If Nakano kept
detailed records of what work Yu Bee’s workers did after January 2000, these were not shown to the
court. Nor were Nakano’s closing submissions helpful in this regard as there was no attempt there
to break down the sum of $971,156.91 into its constituent items or to give detailed justifications
of the individual components. Accordingly, I cannot make any award in relation to Yu Bee’s
invoices. (4) Hai Hwa’s and Kan Leong’s invoices 160. Hai Hwa and Kan Leong were the other two third party sub-contractors engaged
to complete the outstanding external plastering works as well as to re-plaster areas that were
hacked by Forest but left unplastered and to touch up uneven surfaces. According to Nakano’s
submission, Hai Hwa and Kan Leong claimed payment for about 28,000 m² of external plastering works
and the difference in their charges and what would have been charged by Forest amounted to
$85,327.89 and $98,875 respectively. 161. In its submissions, Nakano did not distinguish between the amount that it
paid to these two sub-contractors for rectification work and the amount that it paid them for
completing the external plastering. As I have stated, Nakano is not entitled to recover any amount
paid for completion work since it should not have terminated Forest’s employment. As there is no
indication of the figures paid in respect of rectification work, I cannot make any award in favour
of Nakano to compensate it for the rectification costs, if any, it paid to Hai Hwa and Kan Leong. (5) Defective tiling works 162. Nakano submitted that there were defective works in the tiling sub-contract.
By this sub-contract, Forest was supposed to carry out the tiling works in all 696 units in the
project. In April 2000, however, Forest’s tiling works were terminated by Nakano because the works
were defective and slow. At that time, Forest had completed tiling in only 72 units. Messrs Wong Kan
Thong was engaged to take over the remaining units. At the same time, Forest’s tilers continued to
rectify the defective works. As they were unable to complete the rectification work, Messrs Wong Kan
Thong had to take those over as well and charged Nakano $13,050 for the same. Nakano seeks to
recover that sum from Forest. 163. The evidence of Mr Koon was that Forest had completed all its tiling work by
June 1999. Thereafter, its workers did rectification work on the tiles as and when the defects were
pointed out by Nakano. These rectification works were completed by December 1999 and Mr Koon stated
that he had not received any further complaint about defective tiling work thereafter. Forest
submitted that the evidence adduced by Nakano did not make it clear what kind of defects were found
in Forest’s tiling works or when these defects occurred. Nor was there any detailed evidence on
the alleged rectification work. 164. I, too, find Nakano’s submissions and evidence on this point to be
perfunctory. I am unable to make a finding in its favour on this issue as it had not been proved. (6) Rental of gondolas and climbing platforms 165. Nakano claims $415,146.62 as the costs of additional rental of the gondolas
and climbing platforms during the period between 15 December 1999 and 31 March 2000. Its case is
that had Forest completed its external plastering works according to sequence and within schedule,
Nakano would not have incurred these additional costs. Whilst Nakano conceded that there may be some
overlap in the claim as the gondolas were also necessary for the painting works, it submitted that
had it not been for Forest’s delay, it would not have been necessary for it to rent the gondolas
and climbing platforms for the additional few months. It should be noted that according to Mr
Hattori’s affidavit, Nakano had to pay for rental of gondolas and climbing platforms right up to
June 2000. Although the rectification works went on till June 2000 and the plastering works by Kan
Leong were completed only at the end of May 2000, Nakano’s claim was up to the end of March 2000
only to take into account that some platforms and gondolas were used for painting. 166. Forest submitted that there is absolutely no merit in this claim. The
gondolas and working platforms were part of the general facilities provided by Nakano for the use of
everyone on site. As Mr Hattori had admitted in cross-examination, these facilities were used by the
other sub-contractors both before and after Forest had left the site. Forest further submitted that
these facilities should be treated in the same way as the tower cranes and other hoisting facilities
provided by Nakano. It did not occur to Mr Hattori that Nakano should claim against Forest for the
costs of supplying these facilities even though the hoisting equipment was used by various
sub-contractors after Forest had left the site. 167. This is another claim which has been insufficiently particularised by
Nakano. The period covered by the claim is from December 1999 to March 2000 whilst the hiring
platforms and gondolas were on site until June 2000. It is not clear whether these platforms and
gondolas were at any time occupied exclusively by plasterers or whether during the whole of the
period they were occupied by both plasterers and painters. A lot of the plaster work had been
completed by the end of December 1999. Even if Nakano’s estimate of 30% of external plaster work
being incomplete at the time of Forest’s termination is accepted as accurate, that would mean that
70% of the plaster work had been completed and that a substantial amount of painting could be done.
Nakano has recognised that it cannot claim hire for the gondolas and platforms during the times that
they were occupied by painters. Seeing that there was overlap in the use of the equipment by
painters and plasterers, it was up to Nakano to establish to my satisfaction how much of the costs
it incurred in hiring the equipment could be attributed solely to the extended plaster works. It did
not do this. It made a rough estimation that that the plaster works took about three and a half
months out of the total six and a half months that it had to continue to hire the gondolas and
climbing platforms. I am not able to award it damages on this basis. (7) Fines and damages 168. Nakano is claiming the sum of $16,000 in respect of fines which it imposed
on Forest during the course of its works and which Forest had not yet paid. It submitted that all
the sub-contractors working on the project had agreed to the system of fines and penalties. The
purpose of these fines was to maintain a safe working environment. The rules and fines were agreed
upon at Safety Committee meetings chaired by the safety officer and attended by the representatives
of the various sub-contractors. Throughout the course of the project, Forest had been fined by
Nakano of various acts of non-compliance with these rules. It had only objected on one occasion when
it was fined for having illegal workers on site. After investigating Forest’s assertion that the
illegal workers were not its employees, Nakano refunded the sum of $3,500 to Forest. 169. Forest submitted that there was no legal basis to justify this claim. I
agree. Simply being the main contractor does not give Nakano a right to fine its sub-contractors for
breach of safety rules and other regulations which it might seek to enforce on site. The
sub-contractor must agree to this situation. Alternatively, there must be a law permitting the
imposition of fines in such circumstances. In this case, neither situation exists. There is no
contractual term allowing Nakano to impose fines on Forest. This claim cannot be allowed either. Conclusion 170. In respect of Forest’s claim, I have found that it is entitled to recover
$1,670,177.96 as the balance due in respect of the works performed by it and the sum of $7,264.24 as
damages for wrongful termination. As against this, I have found that Nakano is entitled to
counterclaim the sum of $734,450 in respect of the costs of rectifying the defective plaster works.
This must be set-off against the amount of Forest’s claim. Forest is therefore entitled to
$942,992.20. 171. I therefore give judgment in favour of Forest in the sum of $942,992.20
together with interest thereon at the rate of 6% per annum from the filing of the writ. As regards
costs, although Forest has succeeded on its claim, it has lost on one major issue ie that relating
to defective works and I think that there should be some adjustment in the costs order to reflect
that. I will therefore hear the parties on costs. Judith Prakash Judge |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| © 2007 Singapore Academy Of Law. All Rights Reserved. Sitemap Terms of Use Disclaimer | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||